File #: 2024-286    Version: 1 Name:
Type: Resolution Status: Passed
File created: 8/30/2024 In control: Board of Directors
On agenda: 9/25/2024 Final action: 9/25/2024
Title: Proposed Amendment No. 3 Contract No. 2000970 Rehabilitation of Screened Final Effluent (SFE) Pump Station CIP# 216008/BCE Score: 63.2
Sponsors: Navid Mehram
Indexes: Wastewater Operations

Title
Proposed Amendment No. 3
Contract No. 2000970
Rehabilitation of Screened Final Effluent (SFE) Pump Station
CIP# 216008/BCE Score: 63.2

Body
Agenda of: September 25, 2024
Item No.: 2024-286
Amount: Original Contract $3,399,730.00
Amendment No. 1 488,611.00
Amendment No. 2 0.00
Proposed Amendment No. 3 0.00
Total Contract Amount $3,888,341.00

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority

DATE: August 30, 2024

RE: Proposed Amendment No. 3
Contract No. 2000970
Rehabilitation of Screened Final Effluent (SFE) Pump Station
Vendor: NORESCO, LLC

MOTION
Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2000970, Proposed Amendment No. 3, "Rehabilitation of Screened Final Effluent (SFE) Pump Station" with NORESCO, LLC, with no increase in cost for a total cost not to exceed $3,888,341.00 and an increased duration of 182 days for a total duration of 1,457 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
GLWA awarded Contract No. 2000970 "Rehabilitation of Screened Final Effluent Pump Station to NORESCO LLC (Design/Build Contractor). The contract is a progressive design build broken into two phases. The first phase (current activities) includes alternative evaluations, basis of design report, 30% design, 60% design, and finally a lump sum price. The second phase will include completing design, construction, startup, commissioning, training, measurement/verification, and guaranteed savings (future amendment, anticipated 2025).
JUSTIFICATION
This proposed extension in the contract time for completion to March 31, 2025, will allow for the com...