Skip to main content
Great Lakes Water Authority Logo
File #: 2026-138    Version: 1 Name:
Type: Resolution Status: New Business
File created: 4/1/2026 In control: Operations and Resources Committee
On agenda: 4/8/2026 Final action:
Title: Proposed Change Order No. 1 Requisition No. REQ-0007283/SCN-0000800 Emergency Construction Contract for Lake Huron Water Treatment Plant High Lift Building Column Repairs CIP #111009 / BCE Score: 75.70
Sponsors: Cheryl Porter
Indexes: Water Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Proposed Change Order No. 1
Requisition No. REQ-0007283/SCN-0000800
Emergency Construction Contract for Lake Huron Water Treatment Plant High Lift Building Column Repairs
CIP #111009 / BCE Score: 75.70
Body
Agenda of: April 22, 2026
Item No.: 2026-138
Amount: Original Contract Price $1,565,950.00
Proposed Change Order No. 1 0.00
Total Contract Amount $1,565,950.00

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority

DATE: April 1, 2026

RE: Requisition No. REQ-0007283/SCN-0000800
Emergency Construction Contract for Lake Huron Water Treatment Plant High Lift Building Column Repairs
Vendor: Pullman SST, Inc.
Status: Amendment/Change Order


MOTION
Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Requisition No. REQ-0007283/SCN-0000800, Proposed Change Order No. 1, "Emergency Construction Contract for Lake Huron Water Treatment Plant High Lift Building Column Repairs" with Pullman SST, Inc., with no increase in cost for a total cost not to exceed $1,565,950.00 and an increased duration of 182 days for a total duration of 322 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.

BACKGROUND
The Lake Huron Water Treatment Plant High Lift Building is constructed with post tensioning cables that are anchored to metal plates that are encased in concrete in the exterior columns. It was observed that the concrete caps were in deteriorated condition and had started to expose metal plates to the elements. A repair detail to replace the concrete caps was developed through Contract No. 1803769 and construction was started through Contract No. 1803990. Work was stopped during demolition when concrete deg...