Title
Proposed Change Order No. 3
Contract No. 2002190
Rehabilitation of Ferric Chloride Feed Systems and Sludge Liner
CIP #211008 / BCE Score: 78.3
Body
Agenda of: June 26, 2024
Item No.: 2024-210
Amount: Original Contract $9,839,000.00
Change Order No. 1 0.00
Change Order No. 2 300,000.00
Proposed Change Order No. 3 0.00
Total Contract Amount $10,139,000.00
TO: The Honorable
Board of Directors
Great Lakes Water Authority
FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority
DATE: May 20, 2024
RE: Proposed Change Order No. 3
Contract No. 2002190
Rehabilitation of Ferric Chloride Feed Systems and Sludge Lines
Vendor: Weiss Construction Co., LLC
MOTION
Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2002190, Proposed Change Order No. 3, "Rehabilitation of Ferric Chloride Feed Systems and Sludge Lines" with Weiss Construction Co., LLC, with no increase in cost for a total cost not to exceed $10,139,000.00 and an increased duration of 183 days for a total duration of 1,348 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
On April 5, 2021, GLWA issued the notice to proceed with Contract No. 2002190, to Weiss Construction Co., LLC. The project is intended to improve reliability of the ferric chloride feed system at Pump Station No. 1 and the Thickened Waste Activated Sludge (TWAS) piping between Complex B and Complex A at the Water Resource Recovery Facility. The scope of work includes replacement of the existing ferric chloride feed sy...