File #: 2026-052    Version: 1 Name:
Type: Resolution Status: New Business
File created: 2/12/2026 In control: Board of Directors
On agenda: 2/25/2026 Final action:
Title: Resolution Regarding Approval of the FY 2027 through FY 2031 Capital Improvement Plan
Sponsors: Jody Caldwell, Dima El-Gamal
Indexes: Planning Services
Attachments: 1. FY 2027-2031 CIP Resolution 2026-052, 2. Proposed Capital Improvement Plan FY 2027-2031, 3. Appendix A Water Business Case Evaluation, 4. Appendix B Wastewater Business Case Evaluation, 5. Appendix C System Background Information, 6. Appendix D Scoring Equation Tech Memo, 7. Appendix E How to Navigate the CIP
Related files: 2025-405, 2025-336, 2025-337, 2026-010
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Resolution Regarding Approval of the FY 2027 through FY 2031 Capital Improvement Plan

Body
Agenda of: February 25, 2026
Item No.: 2026-052

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority

DATE: February 25, 2026 ?
?
RE: Resolution Regarding Approval of the FY 2027 through FY 2031 Capital Improvement Plan?
MOTION
Upon recommendation of Jody Caldwell, Chief Planning Officer, The Board of Directors for the Great Lakes Water Authority (GLWA), adopts the resolution supporting the Capital Improvement Plan (CIP) for Fiscal Years 2027 through 2031, and authorizes the Chief Executive Officer to approve the five year Capital Improvement Plan (CIP) for Fiscal Years 2027 through 2031, including the ten year outlook, noting an affirmative vote of at least five (5) Board Members is necessary for approval of this Motion; and also authorizes the Chief Executive Officer to take such other action as may be necessary to accomplish the intent of this vote.?????
JUSTIFICATION
A capital improvement plan addresses the following objectives:??
1. Identifies an organization's priorities within available resources over a multipleyear period.??
2. Communicates the scope, funding, and timing to stakeholders, coordinating agencies, investors, and the public.???
3. Encompasses stakeholder engagement in its development.?
4. Aligns with strategic objectives of the organization, including effective capital delivery and regulatory compliance at the lowest cost of capital investment.?
?? BUDGET IMPACT
The FY 2027 through FY 2031 Capital Improvement Plan identifies $1.191 Billion of water system capital improvements and $1.268 Billion of sewer system improvements.

COMMITTEE REVIEW
The Capital Planning Committee reviewed Preliminary Drafts of the CIP on October 21, 2025, and December 9, 2025.? Th...

Click here for full text