File #: 2022-561    Version: 1 Name:
Type: Resolution Status: Passed
File created: 12/2/2022 In control: Board of Directors Workshop Meeting
On agenda: 12/14/2022 Final action: 12/14/2022
Title: Proposed Change Order No. 1 Contract No. 2100575 CSO Facility Emergency Generator Improvements CIP #260622/BCE Score: N/A
Sponsors: Navid Mehram
Indexes: Wastewater Operations

Title
Proposed Change Order No. 1
Contract No. 2100575
CSO Facility Emergency Generator Improvements
CIP #260622/BCE Score: N/A

Body
Agenda of: December 14, 2022
Item No.: 2022-561
Amount: Original Contract $1,029,090.00
Proposed Change Order No. 1 0.00
Total Revised Contract $1,029,090.00
TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority

DATE: December 2, 2022

RE: Proposed Change Order No. 1
Contract No. 2100575
CSO Facility Emergency Generator Improvements
Vendor: Rotor Electric Co.

MOTION
Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2100575, Proposed Change Order No. 1, "CSO Facility Emergency Generator Improvements" with Rotor Electric Co., with no increase in cost, for a total cost not to exceed $1,029,000.00 and an increased duration of 180 days for a total contract duration of 540 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
On February 23, 2022, GLWA Board of Directors Authorized the rehabilitation of the Emergency Generators for the nine (9) Combined Sewer Overflow (CSO) facilities GLWA operates.
GLWA contractor Rotor Electric Co. has been coordinating with all the various suppliers to confirm delivery dates for equipment since the beginning of the project. However, due to the ongoing Global chip shortage, a significant lead time for some of the materials and equipment for this project are experiencing lead times that are longer than originally anticipated during bid time for this project. Currently, an extension to the contr...