Title
Proposed Change Order No. 7
Contract No. 1903598/SCN-0000331
Construction Manager at Risk for the Assessment and Rehabilitation of WRRF Yard Piping and Underground Utilities
CIP #216006/BCE Score: 79.00
Body
Agenda of: May 28, 2025
Item No.: 2025-148
Amount: Original Contract $4,863,051.00
Change Order No. 1 685,450.00
Change Order No. 2 596.779.00
Change Order No. 3 0.00
Change Order No. 4 5,000,000.00
Change Order No. 5 9,483,057.00
Change Order No. 6 4,486,693.00
Proposed Change Order No. 7 759,683.00
New Contract Total $25,874,713.00
TO: The Honorable
Board of Directors
Great Lakes Water Authority
FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority
DATE: April 28, 2025
RE: Contract No. 1903598/SCN-0000331
Construction Manager at Risk for the Assessment and Rehabilitation of WRRF Yard Piping and Underground Utilities
Vendor: The Christman Company
Status: Amendment/Change Order
MOTION
Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1903598/SCN-0000331, Proposed Change Order No. 7, "Construction Manager at Risk for the Assessment and Rehabilitation of WRRF Yard Piping and Underground Utilities" with The Christman Company, at an increased cost of $759,683.00 for a total cost not to exceed $25,874,713.00 with an increased duration of 365 days for a total duration of 2,178 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
GLWA awarded Contract No. 1903598 (Construction Manager at Risk (CMAR) for the Assessment and Rehabilitation of the Water Resource Recovery Facility (WRRF) Yard Piping and Underground Utilities to The Christman Company (TCC) (Co...