Proposed Change Order No. 3
Contract No. 2004082
Rehabilitation of Woodward Sewer System
CIP #260207/BCE Score: N/A

Body
Agenda of: May 22, 2024
Item No.: 2024-173
Amount: Original Contract Price $18,696,250.00
Change Order No. 1 0.00
Change Order No. 2 0.00
Proposed Change Order No. 3 0.00
New Contract Total $18,696,250.00

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority

DATE: April 29, 2024

RE: Proposed Change Order No. 3
Contract No. 2004082
Rehabilitation of Woodward Sewer System
Vendor: Lanzo Construction Co.

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2004082, Proposed Change Order No. 3, "Rehabilitation of Woodward Sewer System" with Lanzo Construction Co., with no increase in cost at a total cost not to exceed $18,695,250.00 and an increased duration of 61 days for a total duration of 1,031 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
The Woodward Sewer System (WWSS) is a major combined sewer interceptor aligned with Woodward Avenue starting at McNichols Road and conveys sewage through the cities of Highland Park and Detroit to the Detroit River Interceptor (DRI). In addition, one leg of the WWSS extends sewer service to the east along Chandler and Clay streets and runs north into the city of Hamtramck. This leg of the sewer, referred to as the WS-300 segment, consists of circular and egg-shaped brick sewers that are being rehabilitated by sliplining and Cured in Place Pipe (CIPP).
Change Order No. 1 extended the contract time for sliplining of the WS-300 sewer to allow for extended material procurement time...