Legislation Details

File #: 2026-373    Version: 1 Name:
Type: Resolution Status: New Business
File created: 9/1/2026 In control: Operations and Resources Committee
On agenda: 9/9/2026 Final action:
Title: Proposed Amendment No. 1 Contract No. 2202164/SCN-0000161 Screening & Grit Transportation and Disposal from WRRF & CSO Facilities O&M
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title
Proposed Amendment No. 1
Contract No. 2202164/SCN-0000161
Screening & Grit Transportation and Disposal from WRRF & CSO Facilities
O&M

Body
Agenda of: September 23, 2026
Item No.: 2026-373
Amount: Original Contract Price $1,998,900.00
Amendment No. 1 3,124,884.10
New Contract Total $5,123,784.10

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority

DATE: September 1, 2026

RE: Proposed Amendment No. 1
Contract No. 2202164/SCN-0000161
Screening & Grit Transportation and Disposal from WRRF & CSO Facilities
Vendor: Waste Management of Michigan, Inc.
Status: Amendment/Change Order

MOTION
Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2202164/SCN-0000161, Proposed Amendment No. 1, “Screening & Grit Transportation and Disposal from WWRF & CSO Facilities” with Waste Management of Michigan, Inc., at an increased cost of $3,124,884.10 for a total cost not to exceed $5,123,784.10 and an increased duration of five (5) years for a total duration of seven (7) years; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
As wastewater enters the Water Resource Recovery Facility (WRRF), the influent pump stations lift the wastewater to an elevation allowing it to flow by gravity through the preliminary and primary treatment processes. The preliminary treatment consists of a bar rack to remove rags, sticks, leaves, etc. They are collectively known as screenings from the wastewater stream. Once the screenings are removed, the inorganic material such as sand will settle in large tanks as grit. The screenings and grit are transported by process equipment and temporarily staged in waste storage bins ...

Click here for full text