File #: 2026-004    Version: 1 Name:
Type: Resolution Status: New Business
File created: 1/5/2026 In control: Operations and Resources Committee
On agenda: 1/14/2026 Final action:
Title: Proposed Change Order No. 1 Contract No. 2004674/SCN-0000441 Engineering, Design, and Construction Assistance Services for North Service Center Pump Station Improvements CIP #132016 / BCE Score: 98.70
Sponsors: Cheryl Porter
Indexes: Water Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Proposed Change Order No. 1
Contract No. 2004674/SCN-0000441
Engineering, Design, and Construction Assistance Services for North Service Center Pump Station Improvements
CIP #132016 / BCE Score: 98.70

Body
Agenda of: January 28, 2026
Item No.: 2026-004
Amount: Original Contract Amount: $14,831,090.36
Proposed Change Order No.1 180,658.00
Total Contract Amount $15,011,748.36

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority

DATE: January 5, 2026

RE: Proposed Change Order No. 1
Contract No. 2004674/SCN-0000441
Engineering, Design, and Construction Assistance Services for North Service Center Pump Station Improvements
Vendor: CDM Smith Michigan, Inc.
Status: Amendment/Change Order


MOTION
Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2004674/SCN-0000441, Proposed Change Order No. 1, "Engineering, Design, and Construction Assistance Services for North Service Center Pump Station Improvements" with CDM Smith Michigan, Inc., for an increased cost of $180,658.00 for a cost not to exceed $15,011,748.36 and no increase in duration for a total duration of 2,545 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
Contract No. 2004674 is a design-bid-build contract focused on the rehabilitation of the North Service Center Pumping Station. The rehabilitation will improve electrical reliability and efficiency. Electrical improvements will include replacement of two (2) switchgears, two (2) variable drives, a unit substation, four (4) excitation systems, and various panelboards. Mechanical improvements include replacement of six (6) horizontal split case pumps and their 2,500 h...

Click here for full text