Skip to main content
Great Lakes Water Authority Logo
File #: 2025-425    Version: 1 Name:
Type: Resolution Status: New Business
File created: 12/29/2025 In control: Operations and Resources Committee
On agenda: 1/14/2026 Final action:
Title: Requisition No. REQ-0004588 CSO Outfall Rehabilitation Phase VI CIP# 260510/BCE Score: 73.8
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Attachments: 1. REQ-0004988.Cost Tabulation - Notice of Respondents, 2. Req-0004588.ProcurementBoardReport
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Requisition No. REQ-0004588

CSO Outfall Rehabilitation Phase VI

CIP# 260510/BCE Score: 73.8

 

Body                     

Agenda of:                     January 28, 2026

Item No.:                     2025-425

Amount:                     $7,589,015.00

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     December 29, 2025

 

RE:                     Requisition No.  REQ-0004588

                     CSO Outfall Rehabilitation Phase VI

                     Vendor: Inland Waters Pollution Control, Inc.

                     Status: New Contract/PO

 

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Requisition No. REQ-0004588, “CSO Outfall Rehabilitation Phase VI” with Inland Waters Pollution Control, Inc., at a cost not to exceed $7,589,015.00 for a duration of 760 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

 

 

BACKGROUND

Outfalls are part of GLWA’s wastewater infrastructure and function as the interface between collector and interceptor sewers. They redirect dry weather flow to the Water Resource Recovery Facility (WRRF) while allowing relief of wet weather flows to the nearby river. GLWA has been proactively working to maintain and repair these facilities. Over the past few years, GLWA has completed rehabilitation of over two (2) dozen outfalls in four (4) project phases and will complete Combined Sewer Overflow (CSO) Outfall Rehabilitation Phase No. V by the end of 2025, rehabilitating another 13 outfalls. The proposed project, CSO Outfall Rehabilitation Phase No. VI, will rehabilitate 19 additional outfalls. These structures are generally located near the Northwest Interceptor alignment from Carbon Street to Berg Road, and discharge into the Rouge River. Constructed between the early to mid-1900s and modified several times since construction, these assets have deteriorated over time.

JUSTIFICATION

Inspections under GLWA Contract No. 2003443 identified several defects at each outfall.  The defects were classified and graded per the National Association of Sewer Service Companies Pipeline Assessment Certification Program, resulting in structural and operational and maintenance defects graded on a scale of one to five (with five being most severe). This project addresses defects graded three to five only, through a variety of in-sewer repairs along with debris removal. It should be noted that eight (8) locations will require extensive rehabilitation, including cured-in-place-pipe lining, replacement of the existing pipe and associated underground structures, and stone rip-rap placement near and within the Rouge River. Rehabilitation of the outfalls will extend the service lives and improve the reliability of these assets. Additionally, this contract proposes safety improvements to access manholes, including access entrance up-sizing, installation of larger and hinged frames and covers, and new steps. This work is proposed under construction Contract No. 2300149 and CIP No. 260510.

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.              

Funding Source: 5421 - Sewage Disposal Construction Fund

Cost Center: 880000 - Capital Improvement Fund

Expense Type: 616900 - Construction

Project: PRJ-260510

 

Estimated Cost by Year and Related Estimating Variance:  See table below.

Fiscal Year                                                                                                                                                   

FY 2026 Plan                                                                                                                              $ 409,486.00

FY 2027 Plan                                                                                                                              4,561,681.00

FY 2028 Plan                                                                                                                              2,617,848.00

Proposed Contract Award                                                                                               7,589,015.00

CIP Draft # 2 FY2027-31 Financial Plan Estimate         9,198,276.00

Estimate Variance                                                                                                                 $ 1,609,261.00

Per the CIP plan, this project was not scheduled to start until FY2028. A budget amendment will be completed to reallocate capital reserve funds for the projected FY2026 and FY2027 plan spend.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on January 14, 2026.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.