Legislation Details

File #: 2026-369    Version: 1 Name:
Type: Resolution Status: New Business
File created: 8/28/2026 In control: Operations and Resources Committee
On agenda: 9/9/2026 Final action:
Title: Proposed Amendment No. 2 Contract No. 2203437/SCN-0000376 Service for All WRRF & CSO Facility Pumps O&M
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Proposed Amendment No. 2

Contract No. 2203437/SCN-0000376

Service for All WRRF & CSO Facility Pumps

O&M

 

Body                     

Agenda of:                     September 23, 2026

Item No.:                     2026-369

Amount:                      Original Contract                                  Detroit Pump & Manufacturing  $1,100,000.00

                                                                                                               Kennedy Industries                     1,100,000.00

Amendment No. 1                                                                                                                                                                           0.00

Proposed Amendment No. 2 Detroit Pump & Manufacturing                         455,000.00                     

                                                                                                                           Kennedy Industries                                1,045,000.00

Contract Total Amount                                                            $3,700,000.00

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     August 28, 2026

 

RE:                     Proposed Amendment No. 2

                     Contract No.  2203437/SCN-0000376

                     Service for All WRRF & CSO Facility Pumps

                     Vendor: Detroit Pump & Manufacturing and Kennedy Industries

                     Status: Amendment/Change Order

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2203437/SCN-0000376, Proposed Amendment No. 2 “Service for All WRRF & CSO Facility Pumps” with Detroit Pump & Manufacturing, for an increased cost of $455,000.00 and Kennedy Industries, for an increased cost of $1,045,000.00 for a total cost not to exceed $3,700,000.00 and an increased duration of 730 days for a total duration of 1,825 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

GLWA utilizes both large and small pumps to lift water for conveyance and treatment of wastewater. The organization operates and maintains pumps for the Water Resource Recovery Facility (WRRF), nine (9) Combined Sewer Overflow Facilities (CSO) and nine (9) Sewer Pumping Stations (SPS). The pumps used in our system vary in size, capacity and functionality. Included are pumps used for combined storm systems, daily sanitary flow, dewatering of tanks, sludge moving, flushing water, chemicals, etc. The wastewater that these pumps convey contains abrasive materials like rocks, gravel, and many other solids, all of which increase the frequency of wear and damage to our pumping equipment.

JUSTIFICATION

Wastewater Operating Services (WOS) consists of the WRRF, nine (9) CSO and nine (9) SPS. This service contract provides continuous pump maintenance and repair services for the WOS. Wastewater pumps for GLWA operate under demanding conditions due to the nature of pumping combined wastewater, which often carries elevated levels of gravel and solids. This abrasive material enters the facility and contributes to increased wear and tear on the equipment, making regular maintenance and repairs essential to ensure reliable operation. The funding for this contract has been exhausted as the team took advantage of the drier than average season, to complete some proactive focused preventative and corrective work.  While also experiencing several unanticipated pump failures.

Additionally, the transition of the combined sanitary pump stations from the Field Services Team to the Conveyance Team increased the number of assets covered by this contract. As a result, equipment at the SPS was added to the list of assets requiring evaluation. This contract assists with repairs, troubleshooting, rebuilding, and training where applicable.

PROJECT MANAGEMENT STATUS

Original Contract Time                                                                    1,095 days (08/01/2023 - 07/31/2026) 

Amendment No. 1                                           0 days

Proposed Amendment No. 2                                             730 days (08/01/2026 - 07/31/2028)                                          

New Contract Time                                                                                      1,825 days (08/01/2023 - 07/31/2028)

 

PROJECT ESTIMATE

Original Contract Price                         Detroit Pump & Manufacturing        $1,100,000.00

                                                                              Kennedy Industries                                           1,100,000.00

Amendment No. 1                     0.00

Proposed Amendment No. 2 Detroit Pump & Manufacturing                          455,000.00                     

                                                                                       Kennedy Industries                                                  1,045,000.00

New Contract Total                                                                                                                 $3,700,000.00

 

FINANCIAL PLAN IMPACT

The current FY 2027 budget and five-year financial plan were based on previous experience and work performed. The use of this service may vary by year. The value of the contract exceeds the current financial plan in total. Therefore, budget amendments may be required for this service. First offsetting other positive variances within other contractual services or repairs and maintenance budgets, then from the unallocated reserve.

Funding Source:                     Operations and Maintenance Budget (5960)

Cost Centers:                     Eight Combined Sewer Overflow basins (892271-892278)

Expense Type:                     Equipment Repairs & Maintenance

Estimated Cost by Year and Related Forecast Variance:

Fiscal Year                                                                                                                              Amount

FY 2024 Amended Budget                                                                                       $372,882.50

FY 2025 Amended Budget                                                                                         704,207.10

FY 2026 Amended Budget                                                                                         608,601.00

FY 2027 Budget                                                                                                              704,800.00

FY 2028 Financial Plan                                                                                         718,400.00

FY 2029 Financial Plan (prorated)                                                 61,108.33

Total Financial Plan                                                                                                         $3,169,998.93

Maximum Requisitions                                                                                    $3,700,000.00

Forecast Variance (Negative)/Positive                                            ($530,001.07)

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on September 9, 2026.

SHARED SERVICES IMPACT

The proposed procurement of this service may be used at facilities outlined in the Shared Services Agreement OPS-008 and shared by the GLWA and DWSD.