Great Lakes Water Authority Logo
File #: 2023-200    Version: 1 Name:
Type: Resolution Status: Passed
File created: 5/23/2023 In control: Board of Directors
On agenda: 6/28/2023 Final action: 6/28/2023
Title: Proposed Change Order No. 1 Contract No. 2001051 Southwest Water Treatment Plant SCADA Network Upgrade CIP #170302 / BCE Score: N/A
Sponsors: Cheryl Porter
Indexes: Water Operations

Title

Proposed Change Order No. 1

Contract No. 2001051

Southwest Water Treatment Plant SCADA Network Upgrade

CIP #170302 / BCE Score: N/A

 

Body

Agenda of:                     June 28, 2023

Item No.:                     2023-200

Amount:                     Original Contract                                                               $7,891,696.00

                                          Proposed Change Order No. 1                                     0.00

                                          Total Revised Contract                                          $7,891,696.00

 

TO:                                          The Honorable

                                          Board of Directors

                                          Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                                          Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     May 26, 2023

 

RE:                                          Proposed Change Order No. 1

                                          Contract No. 2001051

                                          Southwest Water Treatment Plant SCADA Network Upgrade

                                          Vendor:  Burns and McDonnell Michigan, Inc.

 

 

MOTION

Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2001051, Proposed Change Order No. 1, “Southwest Water Treatment Plant SCADA Network Upgrades” with Burns and McDonnell Michigan, Inc., with no increase in cost for a total cost not to exceed $7,891,696.00 and an increased duration of 304 days for a total duration of 1,034 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

 

 

BACKGROUND

The intent of the Southwest Water Treatment Plant Supervisory Control and Data Acquisition (SCADA) Network Upgrade project is to replace the plant’s obsolete control systems and existing control networks.  Under this project, the vendor is providing the engineering design, demolition, furnishing of field devices, equipment, local control panels, installation, and start-up of a complete advanced plant-wide SCADA control system and networks, that meets the current GLWA SCADA Governance Documents standards. 

Contract No. 2001051 is a design build project which is in the construction installation phase of the networks backbone and installation of the local controls panels for the plants, network, chemical and process systems.  Contract No. 2001051 was awarded to Burns and McDonnell Michigan, Inc. on February 24, 2021, and the notice to proceed was
July 1, 2021.  This proposed change order would extend the substantial completion and final completion dates to February 23, 2024, and April 30, 2024, respectively.

JUSTIFICATION

The Contractor requested a time extension stating instrumentation and electrical suppliers are unable to receive individual parts from Original Equipment Manufacturer (OEM) manufacturers that are required to produce the instrument/electrical equipment needed to assemble the final equipment required under this project (e.g., control panels, network switches, etc.)  Additionally, the current disruptions in the supply chain of equipment are also causing delivery delays.

PROJECT MANAGEMENT STATUS

Original Contract Time                                              730 days                     (07/01/2021 - 07/01/2023)

Proposed Change Order No. 1                        304 days                     (07/02/2023 - 04/30/2024)

New Contract Time                                                                1,034 days                     (07/01/2021 - 04/30/2024)

PROJECT ESTIMATE

Original Contract Price                                                                $7,891,696.00

Proposed Change Order No. 1                                                                    0.00

New Contract Total                                                                           $7,891,696.00

 

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.

Funding Source: Water Construction Fund

Cost Center: Water Engineering

Expense Type: Construction (5421-892211.000-616900-170302)

Estimated Cost by Year and Related Estimating Variance:  N/A

This proposed amendment is for an extension of time only. Although the amendment extends the final completion date into FY 2024, there is no substantive financial impact.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on June 14, 2023. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.