File #: 2023-439    Version: 1 Name:
Type: Resolution Status: Passed
File created: 11/16/2023 In control: Board of Directors Workshop Meeting
On agenda: 12/13/2023 Final action: 12/13/2023
Title: Proposed Amendment No. 2 Contract No. 2002946 Environmental Health and Safety Compliance Services O & M
Sponsors: William Wolfson
Indexes: Administration & Compliance

Title

Proposed Amendment No. 2

Contract No. 2002946

Environmental Health and Safety Compliance Services                     

O & M

 

Body

Agenda of:                     December 13, 2023

Item No.                     2023-439

Amount:                     Original Contract:                                              $2,000,000.00

Amendment No. 1:                                         0.00

Amendment No. 2:                             0.00

                                           New Contract Total:                                          $2,000,000.00

 

TO:                     The Honorable

Board of Directors

Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

Chief Executive Officer

Great Lakes Water Authority

 

DATE:                     November 16, 2023

 

RE:                                          Proposed Amendment No. 2

Contract No. 2002946

Environmental Health and Safety Compliance Services

Vendor:  NTH Consultants, Ltd

 

MOTION

 

Upon recommendation of William Wolfson, Chief Administrative and Compliance Officer/Interim General Counsel, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2002946, Proposed Amendment No. 2, “Environmental Health and Safety Compliance Services” with NTH Consultants, LTD, with no increase in cost for a total cost not to exceed $2,000,00.00 and an increased duration of one (1) year for a total duration of four (4) years; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.  

 

BACKGROUND

 

The Great Lakes Water Authority’s (GLWA) Enterprise Risk Management Safety group is committed to continuously improve environmental health and safety at GLWA and to increase environmental/occupational health and safety awareness for all GLWA, employees, visitors, contractors, and the communities surrounding our facilities. The current environmental safety contract (2002946) has expired after two years. This contract was for $2 million over two years (average of $1,000,000 per year). At the end of the contract period, the spend was just above $500,000 over the two-year period ($1.4 million favorable variance).

 

JUSTIFICATION

 

This proposed Contract extension for time is to continue providing environmental-occupational health and safety consulting including response services, waste removal and disposal, and regulatory compliance assistance on an as-needed basis for an additional one year. The Consultant’s response time for any emergency cleanup work shall be immediate and shall not exceed twenty-four (24) hours, depending on the size and seriousness of the incident. The consultant will assist in performing environmental compliance audits of various GLWA facilities, continue to develop finalize Spill Prevention, Control, and Countermeasures (SPCC) plans, Pollution Incident Prevention (PIP) plans, Process Safety Management (PSM) plans, and Risk Management Plan  (RMP) submittals, and MEARS air reporting to the State of Michigan. In addition, the vendor will provide or procure appropriate training by experienced instructors to GLWA personnel to maintain compliance with each plan’s requirements.

 

PROJECT MANAGEMENT STATUS

 

Original Contract Time                                           2 years                      (01/01/2021 - 12/31/2022)

Amendment ​No. 1​                                                                1 year                      (01/01/2023 - 12/31/2023)

Proposed Amendment No. 2                     1 year                        (01/01/2024 - 12/31/2024)

New Contract Time                                                                4 years                        (01/01/2021 - 12/31/2024)

 

 

 

 

 

PROJECT ESTIMATE

 

Original Contract Price                                           $ 2,000,000.00

Amendment No. 1                                                               $ 0.00

Amendment No. 2                                                               $ 0.00

New Contract Total                                                                $ 2,000,000.00

 

FINANCIAL PLAN IMPACT

 

Summary: Sufficient funds are provided in the financial plan for this project. 

Funding Source: Operations & Maintenance (O&M) Budget

Cost Center(s): Enterprise Risk Management and Safety (883401) 

Expense Type: Contractual Operating Services (5910-883401.000-617900-WS7900) 

Estimated Cost by Year and Related Forecast Variance: See table below.

Fiscal Year                                                                                                                               Amount

FY 2024 Budget                                                                                             $   500,000.00

FY 2025 Financial Plan                                                                                    1,000,000.00

FY 2026 Financial Plan                                                                                       500,000.00

Financial Plan Forecast                                                                         $2,000,000.00

Proposed Contract Amount                                                    $2,000,000.00

Variance (positive/ (negative)                           $              0.00

 

COMMITTEE REVIEW 

 

This item was presented to the Operations and Resources Committee at its meeting on December 13, 2023. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

 

SHARED SERVICES IMPACT 

 

This item does not impact the shared services agreement between GLWA and DWSD.