Great Lakes Water Authority Logo
File #: 2024-285    Version: 1 Name:
Type: Resolution Status: New Business
File created: 8/30/2024 In control: Board of Directors
On agenda: 9/25/2024 Final action:
Title: Proposed Amendment No. 3 Contract No. 1904337 WRRF PS-2 Bar Racks Replacements and Grit Collection System Improvements CIP #211007/BCE Score: 75.7
Sponsors: Navid Mehram
Indexes: Wastewater Operations

Title

Proposed Amendment No. 3

Contract No. 1904337

WRRF PS-2 Bar Racks Replacements and Grit Collection System Improvements

CIP #211007/BCE Score: 75.7

 

Body

Agenda of:                     September 25, 2024

Item No.:                     2024-285

Amount:                     Original Contract                                                                                     $11,307,128.58

                                          Amendment No. 1                                                                                           496,159.80

                                          Amendment No. 2                                                                                                                0.00

                                          Proposed Amendment No. 3                                              5,386,323.63

Total Contract Amount                                            $17,189,612.01

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     August 30, 2024

 

RE:                                          Proposed Amendment No. 3

                     Contract No. 1904337

                     WRRF PS-2 Bar Racks Replacements and Grit Collection System Improvements

                     Vendor:  Hazen and Sawyer

                     

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1904337, Proposed Amendment No. 3, “WRRF PS-2 Bar Racks Replacements and Grit Collection System Improvements” with Hazen and Sawyer, at an increased cost of  $5,386,323.63 for a total cost not to exceed $17,189,612.01 and an increased duration of 132 days for a total duration of 2,535 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

GLWA contracted the engineering firm of Hazen and Sawyer in October 2020 to perform planning, preliminary design, detailed design, and construction services for the Pump Station-2 Bar Racks Replacements and Grit Collection System Improvements (PS2RG) project.

Project improvements include:

                     Replacing the existing bar screens with new screens that have narrower openings.

                     Replacing the existing screenings conveyor belt with a sluicing trough flowing to dual drum screen and compactors.

                     Retrofitting the existing aerated grit tanks with vortex grit removal technology.

                     Building a new grit processing facility including grit classifiers paired to each vortex grit tank for grit washing/dewatering.

The PS2RG improvements will significantly improve the removal of screenings and grit through smaller opening sized screens and enhanced grit removal systems.  The removal of more material at the plant influent will reduce Water Resource Recovery Facility (WRRF) operation and maintenance costs by reducing debris and grit which cause equipment failures in downstream plant processes.

The existing design engineering services agreement with Hazen and Sawyer includes limited construction administrative services (such as shop drawing review, training content review, update of Operations and Maintenance manuals, and limited special inspections) but did not include full construction services because the consultant would have had difficulty establishing costs for this with a yet to be determined design.  This amendment expands the scope of that agreement to include the following additional services:

                     Construction Contract Administration (CCA): Dedicated oversight and management of the construction contract, including ensuring compliance with contractual requirements, issue resolution, and timely execution.

 

                     Inspection: Field observation professionals will be on-site to monitor construction activities, address any issues promptly, and facilitate communication between stakeholders.

 

                     Project construction permit coordination.

JUSTIFICATION

The Pump Station 2 Bar Racks and Grit Improvements project is the largest single capital investment in the history of the WRRF.  The construction is extraordinarily complex, including technically demanding concrete demolition, substantial modifications to multiple buildings, installation of new processing technologies, and maintenance of screening and grit removal operations throughout the 8-year long construction project.  GLWA is increasing the planning and administrative support to match the needs and importance of this effort. This work was added to the existing scope of work with Hazen and Sawyer because of the efficiency gained by their expertise on the project design and allows for project continuity to ensure successful delivery of the construction project.

PROJECT MANAGEMENT STATUS

Original Contract Time                                           2,403 days (10/20/2020 - 05/19/2027)

Amendment No. 1                                                                     0 days

Amendment No. 2                                                                     0 days

Proposed Amendment No. 3                        132 days (05/20/2027 - 09/28/2027)

New Contract Time                                                                2,535 days (10/20/2020 - 09/28/2027)

PROJECT ESTIMATE

Original Contract Price                                            $11,307,128.58

Amendment No. 1                                                                       496,159.80

Amendment No. 2                                                                                            0.00

Proposed Amendment No. 3                           5,386,323.63                     

New Contract Total                                                                 $17,189,612.01

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.              

Funding Source: Wastewater Construction Bond

Cost Center: Sewer Water

Expense Type: Design Build (5421-892211.000-617950-211007)

Estimated Cost by Year and Related Estimating Variance:  See table below.

Original Contract Price                                                           $11,307,128.58

Amendment No. 1                                                                                                                                                               496,159.80

Amendment No. 2                                                                                                                                              0.00

Proposed Amendment No. 3                                                                                                5,386,323.63

New Contract Total                                                                      $17,189,612.01

Amended Financial Plan Estimate:                                           11,803,288.38

Estimating Variance                                                                 ($5,386,323,63)          

 

If approved, Proposed Amendment No. 3, a negative estimated variance of ($5,386,323,63) is created.  This variance will be funded from Capital Reserves.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on September 11, 2024. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.