File #: 2025-401    Version: 1 Name:
Type: Resolution Status: New Business
File created: 11/25/2025 In control: Operations and Resources Committee
On agenda: 12/10/2025 Final action:
Title: Proposed Change Order No. 2 Contract No. 2201762/SCN-0000301 PS1 Rack and Grit HVAC Upgrade CIP #211011/ BCE Score: 77.50
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Proposed Change Order No. 2

Contract No. 2201762/SCN-0000301

PS1 Rack and Grit HVAC Upgrade

CIP #211011/ BCE Score: 77.50

 

Body                     

Agenda of:                     December 10, 2025

Item No.:                     2025-401

Amount:                     Original Contract                                                                $5,294,101.00

                                          Change Order No.1                                                                                         0.00

                                          Proposed Change Order No. 2                                               0.00

                                          Total Contract Amount                                          $5,294,101.00

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     November 25, 2025

 

RE:                     Proposed Change Order No. 2

                     Contract No.  2201762/SCN-0000301

                     PS1 Rack and Grit HVAC Upgrade

                     Vendor: Clark Construction Company

                     Status: Amendment/Change Order

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No 2201762/SCN-0000301, Proposed Change Order No. 2, “PS1 Rack and Grit HVAC Upgrade” with Clark Construction Company, with no increase in cost for a cost not to exceed $5,294,101.00 and an increase duration of 106 days for a total duration of 1,143; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.

BACKGROUND

On February 13, 2023, GLWA awarded Contract No. 2201762, titled “Pump Station No. 1 (PS-1) Rack and Grit HVAC System Upgrade,” to Clark Construction Company (Clark), with a start date of March 1, 2023. The scope of work under this contract includes, but is not limited to, the replacement of existing roof-mounted air handling units, associated ductwork, natural gas piping, controls, and related appurtenances; removal of existing steam unit heaters and their associated components; and the furnishing and installation of new exhaust fans and other items as detailed in the contract documents.

JUSTIFICATION

As of November 20, 2025, all construction elements of this project have been completed.  This extension in time is to allow time for the processing of the final change order, final pay application, and to complete the final administrative elements necessary to close out this project. 

PROJECT MANAGEMENT STATUS

Original Contract Time                                            920 days (03/01/2023 - 09/06/2025)

Change Order No. 1                                            117 days (09/06/2025 - 12/31/2025)

Proposed Change Order No. 2                      106 days (12/31/2025 - 04/15/2026)

New Contract Time                                                    1,143 days (03/01/2023 - 04/15/2026)

 

 

PROJECT ESTIMATE

Original Contract Price                                            $5,294,101.00

Change Order No. 1                                                                       0.00                     

Proposed Change Order No. 2                                                0.00

New Contract Total                                                                 $5,294,101.00

 

 

 

 

FINANCIAL PLAN IMPACT              

Funding Source: 5421 - Wastewater Construction Fund

Cost Center: 880000 - Capital Improvement Program

Spend Category: Construction

Project Worktag: PRJ-211011

Estimated Cost by Year and Related Estimating Variance: See table below.

Original Contract Price                                                     $5,294,101.00

Change Order No.1                                                                                                                                                 0.00

Proposed Change Order No. 2                                                                        0.00

New Contract Total:                                                                                                   $5,294,101.00

Amended Financial Plan Estimate                                      5,294,101.00

Estimating Variance:                                                                         0.00

 

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on December 10, 2025.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.