Title: Requisition No. REQ-0006884 Reservoir Rehabilitation Phase III CIP #170803 / BCE Score 90.3
Sponsors: Cheryl Porter
Indexes: Water Operations
Attachments: 1. REQ-0006884 Procurement Board Report, 2. REQ-0006884 Cost Comparison, 3. REQ-0006884 Cost Tabulation - Notice of Respondents
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Requisition No. REQ-0006884

Reservoir Rehabilitation Phase III

CIP #170803 / BCE Score 90.3

Body

Agenda of:                     October 28, 2026

Item No.:                     2026-403

Amount:                     $51,998,000.00

 

TO:                                          The Honorable

                                          Board of Directors

                                          Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                                          Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     September 30, 2026

 

RE:                                          Requisition No. REQ-0006884

                                          Reservoir Rehabilitation Phase III

                                          Vendor: Pullman SST, Inc.

                                          Status: New Contract/PO

 

MOTION

Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Requisition No. REQ-0006884, “Rehabilitation Phase III” with Pullman SST, Inc., at a cost not to exceed $51,998,000.00 for a duration of 2,100 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

The Great Lakes Water Authority (GLWA) operates 30 finished drinking water reservoirs.  Inspection, repair, and cleaning of the reservoirs on a regular interval is mandated by the Michigan Department of Environment, Great Lakes, and Energy (EGLE) and performed under GLWA capital improvement maintenance program 170800. Currently, 21 reservoirs have been cleaned, inspected and rehabilitated since 2020 under the first and second phase of the CIP programs, 170801 and 170802. The next phase of inspections on 14 reservoirs is being performed under a design-build delivery method and will return back to the reservoirs inspected in Phase I.  GLWA water engineering developed and issued the indicative design documents used to procure the contract for Phase III. The proposed design-build contract will include inspection, cleaning, and rehabilitation work on 14 finished drinking water reservoirs.  GLWA plans to inspect and rehabilitate the reservoirs over a four-year period starting in the fall of 2027 (FY2028) and concluding in the spring of 2031 (FY2031).  The reservoirs are located at the following GLWA facilities: 

•                     Lake Huron Water Treatment Plant (WTP) (3 reservoirs)

•                     Springwells WTP (3 reservoirs)

•                     Southwest WTP (3 reservoirs)

•                     Wick Road Booster Station (1 reservoir)

•                     Schoolcraft Station (1 reservoir)

•                     West Service Center (2 reservoirs)

•                     Imlay Station (1 reservoir)

 

The rehabilitation work includes concrete repairs, expansion joint replacement, hatch and ladder repair, as needed air vent screen replacement, roofing membrane repair and replacement, reservoir overflow rehabilitation, in-reservoir piping repairs/coating.  Underdrain inspections and underdrain pump replacement, painting of carbon steel components, electrical controls and receptacle installation and repair, and site work improvements.  The proposed contract contains lump sum work, unit price work, and job order issued allowance work.  Unit price work will be paid based on actual quantities installed as identified by the Engineer.

JUSTIFICATION

Finished water reservoirs must be inspected on regular intervals to comply with EGLE regulatory requirements. Furthermore, inspection and rehabilitation of GLWA’s finished water reservoirs on a regular schedule is the preferred approach to proactively maintain and ensure reservoir integrity and safe finished drinking water quality.                     

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.

Funding Source: 5519 - Water Construction Fund

Cost Center: 880000 - Capital Improvement Fund

Expense Type: 616900 - Construction

Project: 170803

 

 

Estimated Cost by Year and Related Estimating Variance: See table below.

Fiscal Year

FY 2027 Planned Spend                                                                                    $     2,575,000.00

FY 2028 Planned Spend                                                                                           7,795,000.00

FY 2029 Planned Spend                                                                                         10,671,000.00

FY 2030 Planned Spend                                                                                         12,324,000.00

FY 2031 Planned Spend                                                                                         10,675,000.00

FY 2032 Planned Spend                                                                                           6,229,000.00

Financial Plan Estimate                                                                                    $   50,269,000.00

Proposed Contract Award                                                                                         51,998,000.00

Estimating Variance                                                                                                         $    (1,729,000.00)

Projects have been reallocated to account for the estimating variance.

COMMITTEE REVIEW

This matter is being presented directly to the GLWA Board of Directors.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.