Skip to main content
Great Lakes Water Authority Logo
File #: 2026-128    Version: 1 Name:
Type: Resolution Status: New Business
File created: 3/27/2026 In control: Operations and Resources Committee
On agenda: 4/8/2026 Final action:
Title: Proposed Amendment No. 7 Contract No. 1903601/SCN-0000356 Yard Piping Engineering Services CIP #216006/BCE: 79.00
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Proposed Amendment No. 7

Contract No. 1903601/SCN-0000356

Yard Piping Engineering Services

CIP #216006/BCE: 79.00

 

Body                     

Agenda of:                     April 22, 2026

Item No.:                     2026-128

Amount:                     Original Contract                                                               $1,647,814.74

Amendment No. 1                                                                    434,722.00

Amendment No. 2                                                                    765,627.00

Amendment No. 3                                                                                         0.00

Amendment No. 4                                                                    764,635.08

Amendment No. 5                                                                 1,332,739.08

Amendment No. 6                                                                    619,202.83

                                    Proposed Amendment No. 7                                                 0.00

Contract Amount                                                               $5,564,740.73                                          

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     March 27, 2026

 

RE:                     Proposed Amendment No. 7

                     Contract No.  1903601/SCN-0000356

                     Yard Piping Engineering Services

                     Vendor: CDM Smith Michigan, Inc.

                     Status: Amendment/Change Order

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1903601/SCN-0000356, Proposed Amendment No. 7 “Yard Piping Engineering Services”, with CDM Smith Michigan, Inc., with no increase in cost for a cost not to exceed  $5,564,740.73 and an increase in duration of 238 days for a total duration of 2,195 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

GLWA awarded Contract No.1903601 “Yard Piping Engineering Services” to CDM Smith Michigan, Inc. (Engineer). The Contract is divided into four (4) major phases: study, preliminary design, final design, and construction.

To date, six (6) amendments have been issued. The purpose of this contract is to provide design services to support the Construction Manager at Risk (CMAR) project which is structured to advance the work through different delivery packages issued via Amendments. This approach allows construction activities to progress while the design continues to be developed, ensuring proper coordination and constructability.

The CMAR contractor under construction Contract No. 1903598 has now achieved Substantial Completion of 19 separate improvements for design/construction and one (1) program for the secondary final effluent valve exercising which has been incorporated in previous amendments to this Contract.

Proposed Amendment No. 7 seeks to extend the contract time to match the contract time for the CMAR construction contract date to allow for final paperwork and project closeout to be completed.

JUSTIFICATION

The proposed no cost Amendment No. 7 for contract time allows CDM Smith to continue working with the CMAR Contractor to complete final project closeout for the improvements completed in the CMAR Yard Piping Contract.                     

 

PROJECT MANAGEMENT STATUS

Original Contract Time                                            792 days (12/28/2020 - 02/27/2023)

Amendment No. 1                                                          0 days

Amendment No. 2                                                                    0 days

Amendment No. 3                                                                215 days (02/28/2023 - 09/30/2023)

Amendment No. 4                                                                243 days (10/01/2023 - 05/30/2024)

Amendment No. 5                                                                442 days (05/31/2024 - 08/15/2025)

Amendment No. 6                                                                265 days (08/16/2025 - 05/07/2026)

Proposed Amendment No. 7                      238 days (05/08/2026 - 12/31/2026)

New Contract Time                                                    2,195 days (12/28/2020 - 12/31/2026)

 

PROJECT ESTIMATE

Original Contract Price                                              $1,647,814.74

Amendment No. 1                                                                       434,722.00

Amendment No. 2                                                                       765,627.00

Amendment No. 3                                                                                            0.00

Amendment No. 4                                                                       764,635.08

Amendment No. 5                                                                    1,332,739.08  

Amendment No. 6                                 619,202.83

Proposed Amendment No. 7                                                   0.00

New Contract Total                                                                   $5,564,740.73

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.             

Funding Source: 5421 - Sewage Disposal Construction Fund

Cost Center: 880000 - Capital Improvement Fund

Expense Type: 616900 - Construction

Project: PRJ-216006

Estimated Cost by Year and Related Estimating Variance: See table below.

Original Contract Price:                                                         $1,647,814.74

Amendment No. 1                                                                             434,722.00

Amendment No. 2                                                                                                                                           765,627.00

Amendment No. 3                                                                                                                                                                0.00

Amendment No. 4                                                                                        764,635.08

Amendment No. 5                                                                   1,332,739.08

Amendment No. 6                                                                      619,202.83 

Proposed Amendment No. 7                                                                0.00 

New Contract Total:                                                                                                                  $5,564,740.73

Amended Financial Plan Estimate:                                         7,517,000.00

Estimating Variance:                                                              $1,952,259.27

 

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on April 8, 2026.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.