Great Lakes Water Authority Logo
File #: 2020-351    Version: 1 Name:
Type: Resolution Status: Passed
File created: 10/7/2020 In control: Board of Directors
On agenda: 10/28/2020 Final action: 10/28/2020
Title: Contract No. 2002048 Phase II - 14 Mile Transmission Main Loop - Double Disc Gate Valves CIP# 122013 / BCE Score: 58.4
Sponsors: Cheryl Porter, Grant Gartrell
Indexes: Water Operations
Attachments: 1. 2002048 Procurement Board Report, 2. 2002048 Cost Tabulation, 3. 2002048 Vendor Response

Title

Contract No. 2002048

Phase II - 14 Mile Transmission Main Loop - Double Disc Gate Valves

CIP# 122013 / BCE Score: 58.4

 

Body                     

Agenda of:                     October 28, 2020

Item No.:                     2020-351

Amount:                      $1,177,770.03

 

TO:                                          The Honorable

                                          Board of Directors

                                          Great Lakes Water Authority

 

FROM:                     Sue F. McCormick

                                          Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     October 7, 2020

 

RE:                                          Contract No. 2002048

                                          Phase II - 14 Mile Transmission Main Loop Project - Double Disc
                                          Gate Valves

                                          Vendor: Kennedy Industries, Inc.

 

 

MOTION

Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2002048 “Phase II - 14 Mile Transmission Main Loop Project - Double Disc Gate Valves” with Kennedy Industries, Inc., at a cost not to exceed $1,177,770.03 for a duration of 1,060 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.

BACKGROUND

The 14 Mile Road transmission main supplies water to the communities of Novi, Farmington Hills, West Bloomfield, Commerce, Walled Lake, and Wixom. If a disruption to service occurs on the 14 Mile transmission system, without the gate valves GLWA may not be able to supply sufficient pressure and may have a boil water advisory.

GLWA proposed a new transmission main loop to connect the 8 Mile and 14 Mile transmission systems in order to provide redundancy to the 14 Mile transmission system. The new transmission main is being constructed in two phases. Phase I is currently under construction and involves installing approximately 1 mile of 24-inch diameter transmission main along 14 Mile Road between M-5 and Decker Road. Phase I started in August 2020 and will be complete by September 2021. Phase II of the project is currently in the design phase (approximately 90% complete) and will involve the construction of a 54-inch diameter transmission main between 8 Mile and 14 Mile Roads. The bidding phase for Phase II construction will commence around January of 2021 and construction is planned to start in the summer of 2021. This proposed Contract No. 2002048 involves the direct purchase of double-disc gate valves to be installed under the Phase II construction of the transmission main. The double-disc gate valves to be purchased include: two 24-inch, one 30-inch, and seven 48-inch diameter valves. Construction of the entire project, including the purchase of the double-disc gate valves under this proposed contract is being funded by State of Michigan Department of Environment, Great Lakes, and Energy Drinking Water Revolving Loan funds.

JUSTIFICATION

The double-disc gate valves to be purchased under this proposed contract have a lead time of approximately 12 months to manufacture and deliver. Therefore, ordering these valves now through this proposed contract will help avoid potential delays during construction due to the associated long lead time.

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.              

Funding Source: Water Construction Bond

Cost Center: Water Engineering

Expense Type: Construction (5519-882411.000-617955-122013)

Estimated Cost by Year and Related Estimating Variance:  See table below.

Fiscal Year

FY 2022 Plan - Phase II                                                                                    $14,168,000.00

FY 2023 Plan - Phase II                                                                                      14,168,000.00

FY 2024 Plan - Phase II                                                                                      14,168,000.00

FY 2025 Plan - Phase II                                                                                      14,168,000.00

  Financial Plan Estimate                                                                          $56,672,000.00

Proposed Contract Award                                                                                        1,177,770.03

Balance Reserved for Construction                                $55,494,229.97

SAVINGS, COST OPTIMIZATION, AND REVENUE ENHANCEMENT IMPACT

This award is for purchase of Phase II - 14 Mile Transmission Main Loop Project - Double Disc Gate Valves.  Cost savings are not determinable at the time of this award.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on October 15, 2020. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.