Great Lakes Water Authority Logo
File #: 2024-237    Version: 1 Name:
Type: Resolution Status: New Business
File created: 6/28/2024 In control: Operations and Resources Committee
On agenda: 7/10/2024 Final action:
Title: Contract No. 2304897 Northwest Interceptor to Oakwood CSO Sewer Construction CIP #222001/BCE Score: 62.7
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Attachments: 1. 2304897 CIP Plan (222001), 2. 2304897 Cost Tabulation - Notice of Respondents, 3. 2304897 Procurement Board Report-RFB
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Contract No. 2304897

Northwest Interceptor to Oakwood CSO Sewer Construction

CIP #222001/BCE Score: 62.7

 

Body

Agenda of:                      July 24, 2024

Item No.:                     2024-237

Amount:                     $73,508,929.00                                                                                                                                                                                             

 

TO:                                          The Honorable

Board of Directors

Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                                          Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     June 28, 2024

 

RE:                     Contract No.  2304897

Northwest Interceptor to Oakwood CSO Sewer Construction

Vendor:  Jay Dee Contractors, Inc

 

MOTION

 

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2304897, “Northwest Interceptor to Oakwood CSO Sewer Construction” with Jay Dee Contractors, Inc, at a cost not to exceed $73,508,929.00 for a duration of 1,461 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

 

 

BACKGROUND

The Northwest interceptor to Oakwood Combined Sewer Overflow sewer (NOCSOs) was conceived of as part of the Wastewater Master Plan to maximize the use of existing facilities to treat wet weather flows. The Oakwood Combined Sewer Overflow (CSO) Retention Basin has historically been underutilized in terms of flow to the facility.  The study and design resulted in this construction project constructing a tunnel to divert excess wet weather flows from the Northwest Interceptor (NWI) to the Oakwood CSO basin for treatment and discharge.

Better utilization of the Oakwood CSO Facility represents strategic planning at GLWA aimed at maximizing the use of our existing infrastructure before constructing additional new facilities to handle the same challenges. The construction of the NOCSOs tunnel will allow flow during high hydraulic grade line (HGL) (Water Level) periods in the NWI to be diverted out of the interceptor to the Oakwood facility for treatment and discharge.  This operation will reduce the HGL in the NWI and allow flows from other parts of the system that would have been untreated CSO discharges or sanitary sewer overflows otherwise to be transported and treated at the Water Resource Recovery Facility (WRRF), or the Oakwood CSO Facility.

JUSTIFICATION

The NOCSOs tunnel will reduce the hydraulic grade line in the NWI downstream of the Warren-Pierson control gate during wet weather events of significant size.  This grade line is created by both high wet well levels at the WRRF, and overloading of the NWI.  Given the historical under-utilization of the Oakwood CSO Facility, this project will allow GLWA to use the excess storm pumping capacity. In a parallel effort, GLWA plans to increase the chemical capacity of the facility to handle longer lasting storms at higher flow rates than originally designed.

Three responsive bids were received for this project. GLWA is recommending approval of Jay Dee Contracting, Inc for the award of the NOCSO tunnel project for construction.

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.         

Funding Source: Wastewater Construction Fund

Cost Center: Wastewater Field Engineering

Expense Type: Construction (5421-892411.000-616900-222001)

Estimated Cost by Year and Related Estimating Variance:  See table below.

Fiscal Year

FY 2025 Plan                                                                                              $                  0.00

FY 2026 Plan                                                                                                           21,387,000.00

FY 2027 Plan                                                                                                           21,387,000.00

FY 2028 Plan                                                                                                           21,445,000.00

FY 2029 Plan                                                                                                           10,781,000.00

Financial Plan Estimate                                                                        $  75,000,000.00

Proposed Contract Award                                                                                      73,508,929.00

Estimating Variance                                                                                             $    1,491,071.00

 

This project has been awarded $55 million Clean Water State Revolving Fund (CWSRF) loan and a $20 million American Rescue Plan Act (ARPA) grant.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on July 10, 2024.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.