File #: 2025-402    Version: 1 Name:
Type: Resolution Status: New Business
File created: 11/25/2025 In control: Operations and Resources Committee
On agenda: 12/10/2025 Final action:
Title: Proposed Amendment No. 4 Contract No. 1904337/SCN-0000409 WRRF PS-2 Bar Racks Replacements and Grit Collection System Improvements CIP #211007/BCE Score: 75.70
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Proposed Amendment No. 4

Contract No. 1904337/SCN-0000409

WRRF PS-2 Bar Racks Replacements and Grit Collection System Improvements

CIP #211007/BCE Score: 75.70

 

Body                     

Agenda of:                     December 10, 2025

Item No.:                     2025-402

Amount:                     Original Contract                                                               $11,307,128.58

                                          Amendment No. 1                                                                      496,159.80

                                          Amendment No. 2                                                                                           0.00

                                          Amendment No. 3                                                         5,386,323.63

                                          Proposed Amendment No. 4                            741,967.80

                                          Total Contract Amount                                           $17,931,579.81

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     November 25, 2025

 

RE:                     Proposed Amendment No. 4

                     Contract No. 1904337/SCN-0000409

                     WRRF PS-2 Bar Racks Replacements and Grit Collection System Improvements

                     Vendor: Hazen and Sawyer

                     Status: Amendment/Change Order

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1904337/SCN-0000409, Proposed Amendment No. 4, “WRRF PS-2 Bar Racks Replacements and Grit Collection System Improvements” with Hazen and Sawyer, for an increased cost of $741,967.80 for a total cost not to exceed $17,931,579.81 and an increased duration of 967 days for a total duration of 3,501 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

The engineering firm Hazen and Sawyer was contracted by GLWA in October 2020 to perform planning, preliminary design, detailed design, and construction services for the Pump Station No. 2 Bar Racks Replacements and Grit Collection System Improvements (PS2RG) project. Improvements include:

                     Replacing the existing bar screens with new screens that have narrower openings.

                     Replacing the existing screenings conveyor belt with a sluicing trough flowing

                     to dual drum screen and compactors.   

                     Retrofitting the existing aerated grit tanks with vortex grit removal technology.

                     Building a new grit processing facility including grit classifiers paired to each vortex

                     grit tank for grit washing/dewatering.

 

The PS2RG improvements will significantly improve the removal of screenings and grit through smaller opening size screens and enhanced grit removal systems. This amendment expands the scope of that agreement to include the following additional service:

Special inspection services - Retain a special inspection agency to ensure the construction project meets the safety and compliance standards identified within Section 1704 of the Michigan Building Code for inspection services identified within the project specifications.

JUSTIFICATION

The Special Inspections are required to ensure construction projects meet safety and compliance standards. Failure to provide special inspections during construction can lead to a lack of quality control and assurance for a construction project.  Therefore, these services were added to the existing scope because of the efficiency gained by incorporating them into ongoing construction services role (e.g., construction contraction administration and field observation). Intertek- PSI (special inspection agency) has the qualifications to meet the SI requirements of the Michigan Building Code and has also performed SI services on behalf of construction contractors on previous GLWA projects.

GLWA Engineering negotiated the overall cost of this amendment and recommended the current change for Special Inspection for the PS2RG project. This Amendment will also align the engineering contract of the project with the Contractor’s construction contract final completion date by adding time.                     

 

PROJECT MANAGEMENT STATUS

Original Contract Time                                            2,403 days (10/20/2020 - 05/19/2027)

Amendment No. 1                                                                       0 days

Amendment No. 2                                                                           0 days

Amendment No. 3                                                                   131 days (05/20/2027 - 09/27/2027)

Proposed Amendment No. 4                         967 days (09/28/2027 - 05/21/2030)

New Contract Time                                                                 3,501 days (10/20/2020 - 05/21/2030)

 

PROJECT ESTIMATE

Original Contract Price                                           $ 11,307,128.58

Amendment No. 1                                                                         496,159.80

Amendment No. 2                                                                                            0.00

Amendment No. 3                                                                    5,386,323.63

Proposed Amendment No. 4                             741,967.80                     

New Contract Total                                                                $ 17,931,579.81

 

FINANCIAL PLAN IMPACT              

Funding Source: 5421 - Wastewater Construction Fund

Cost Center: 880000 - Capital Improvement Program

Spend Category: Construction

Project Worktag: PRJ-211007

Estimated Cost by Year and Related Estimating Variance: See table below.

Original Contract Price                                                      $11,307,128.58

Amendment No. 1                                                                                                                               496,159.80

Amendment No. 2                                                                                                  0.00

Amendment No. 3                                                                                   5,386,323.63

Proposed Amendment No. 4                                                    741,967.80

New Contract Total:                                                                                                   $17,931,579.81

Amended Financial Plan Estimate                                      17,930,000.00

Estimating Variance:                                                                 ($1,579.81)

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on December 10, 2025.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.