Title: Proposed Change Order No. 2 Contract No. 2102859/SCN-0000321 Conveyance System Infrastructure Improvements CIP #260701 / BCE Score: 60.10
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Proposed Change Order No. 2

Contract No. 2102859/SCN-0000321

Conveyance System Infrastructure Improvements

CIP #260701 / BCE Score: 60.10

 

..Body                     

Agenda of:                     January 28, 2026

Item No.:                     2025-428

Amount:                     Original Contract Price:                                          $36,863,000.00

                                          Change Order No. 1                                                                      0.00

                                          Proposed Change Order No. 2                                                 0.00

                                          Contract Total                                                               $36,863,000.00

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     December 29, 2025

 

RE:                     Proposed Change Order No. 2

                     Contract No.  2102859/SCN-0000321

                     Conveyance System Infrastructure Improvements

                     Vendor: Jay Dee Contractors, Inc.

                     Status: Amendment/Change Order

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2102859/SCN-0000321, Proposed Change Order No. 2, “Conveyance System Infrastructure Improvements” with Jay Dee Contractors, Inc. with no increase in cost for a total cost not to exceed $36,863,000.00 and an increased duration of 365 days for a total  duration of 1,520 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

 

BACKGROUND

GLWA is responsible for the operation and maintenance of Combined Sewer Overflow (CSO) outfalls on the Detroit and Rouge Rivers. Each of these outfalls are critical wastewater infrastructures that convey flows to relieve the system when the regional system is overwhelmed.  These outfalls are made up of connecting sewers, diversion dams, regulator gates, and backwater gates and come in different configurations thereof. These outfalls were constructed long before the main interceptors were constructed and represent some of the oldest pipes under operation by GLWA.  Each outfall’s independent configuration leads to site specific challenges and obstacles that must be overcome to complete the rehabilitation work. These outfalls are being rehabilitated under this Contract.

JUSTIFICATION

This Proposed Change Order No. 2 is required to provide sufficient contract time to allow the Contractor to perform additional work made necessary by a differing site condition encountered at several of the outfall locations, as well as contract time to perform additional work as directed under the Provisional Allowance for Engineer directed repairs. This change order also provides additional time beyond the final completion milestone to allow GLWA to complete administrative efforts associated with the contract close-out.                     

PROJECT MANAGEMENT STATUS

Original Contract Time                                            790 days (11/11/2022 - 12/09/2024)

Change Order No. 1                                            365 days (12/09/2024 - 12/09/2025)

Proposed Change Order No. 2                      365 days (12/09/2025 - 12/09/2026)

New Contract Time                                                    1,520 days (11/11/2022 - 12/09/2026)

 

PROJECT ESTIMATE

Original Contract Price                                            $36,863,000.00

Change Order No. 1                                                    0.00

Proposed Change Order No. 2                        0.00

New Contract Total                                                                 $36,863,000.00

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.          

Funding Source: 5421 - Wastewater Construction Fund

Cost Center: 880000 - Wastewater Field Engineering

Spend Category: Construction

Project Worktag: PRJ-260701

Estimated Cost by Year and Related Estimating Variance:  See table below.

Original Contract Price                                                                        $36,863,000.00

Change Order No. 1                                                                                                    0.00

Proposed Change Order No. 2                                                                               0.00

New Contract Total                                                                                                         36,863,000.00

Amended Financial Plan Estimate                                          36,863,000.00

Estimating Variance                                                                                                             $0.00

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on January 14, 2026.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.