Great Lakes Water Authority Logo
File #: 2023-395    Version: 1 Name:
Type: Resolution Status: Passed
File created: 10/25/2023 In control: Board of Directors
On agenda: 11/16/2023 Final action: 11/16/2023
Title: Proposed Change Order No. 1 Contract No. 2101610 Magnetic Flow Meter Replacement for Circular Primary Clarifiers O&M
Sponsors: Navid Mehram, Christopher Nastally
Indexes: Wastewater Operations

Title

Proposed Change Order No. 1

Contract No. 2101610

Magnetic Flow Meter Replacement for Circular Primary Clarifiers                     

O&M

 

Body

Agenda of:                      November 16, 2023

Item No.:                     2023-395

Amount:                     Original Contract                                                               $1,495,200.00

                                          Proposed Change Order No.1                          300,000.00

                                          Total Revised Contract                                          $1,795,200.00                                                                                                                                                                                                                  

TO:                                          The Honorable

Board of Directors

Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                                          Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     October 27, 2023

 

RE:                                          Proposed Change Order No. 1

                     Contract No.:   2101610

                     Magnetic Flow Meter Replacement for Circular Primary Clarifiers

                     Vendor:  Rotor Electric Company of Michigan, LLC

 

MOTION

 

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2101610, Proposed Change Order No. 1, “Magnetic Flow Meter Replacement for Circular Primary Clarifiers” with Rotor Electric Company of Michigan, LLC, with an increased cost of $300,000.00 for a total cost not to exceed $1,795,200.00, and an increased duration of 366 days for a total duration of 914 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

The GLWA Water Resource Recovery Facility has six circular primary clarifiers. The flow meters that provide flow information to each clarifier are inoperable, which causes difficulties for operators to properly balance the flow from Pump Station No. 2 to the clarifiers. This project replaces the six existing 96” inch diameter flow meters with new magnetic flow meters to restore proper operations and provide accurate information to operations to balance flows throughout all primary circular clarifiers.

Magnetic flow meters of this size are custom and manufactured upon order. The manufacturer’s lead time for these flow meters is nearly nine months, and the manufacturer is in Germany, further making the ordering and coordination of this work complicated.

During installation of the first flow meter, differing unique site conditions were encountered that affect the fit of the new flow meter to the existing piping on either side of the meter.  Necessary changes are needed to facilitate the installation of the flow meter.

JUSTIFICATION

The construction of this project requires a primary circular clarifier to be taken out of service to allow for the construction. Currently, one unit is out of service and construction activities are underway. Upon dismantling the existing meter, the piping was found to be misaligned with differing conditions than anticipated. This requires additional field modifications with an alternative connection to adequately install the new Mag meter.

The existing provisional allowance for the project was $15,000.00 and has been fully exhausted. Additional funding and time are necessary to complete this project. Therefore, GLWA Wastewater Engineering is recommending extending the existing contract by 366 days and adding 300,000.00 to the contract allowance to facilitate this additional work. The requested amount anticipates similar conditions for the remaining five meters.

PROJECT MANAGEMENT STATUS

Original Contract Time                                           548 days (07/25/2022 - 01/23/2024)

Proposed Change Order No. 1                     366 days (01/24/2024 - 01/23/2025)

New Contract Time                                                                914 days (07/25/2022 - 01/23/2025)

 

 

 

PROJECT ESTIMATE

Original Contract Price                                            $1,495,200.00

Proposed Change Order No. 1                           300,000.00

New Contract Total                                                                 $1,795,200.00

FINANCIAL PLAN IMPACT

Summary:  The replacement of magnetic flow meters project extension was not anticipated during the development of the Capital Outlay budget and exceeds the budget for Flow Measuring and Meters.  Individual projects budgeted in the Capital Outlay are subject to change based on criticality and condition assessment of assets on an on-going basis. These changes are anticipated as changes are made under the Scheduled Replacement Program (SRP). A budget amendment is anticipated drawing first from other projects which may be changed and finally from the Reserves.

Funding Source: Improvement and Extension Fund (I&E)

Cost Center: Wastewater Primary Process (892223)

Expense Type:  Capital Outlay over $5k (I&E-Capitalized) (901100)

Estimated Cost by Year and Related Forecast Variance:  See table below.   

       Fiscal Year                                                                                            Amount          

FY 2022 Budget (Prorated)                                              $82,792.00                                       

FY 2023 Budget (Amended)                                                   662,500.00

FY 2024 Budget                                                                                             146,500.00

FY 2025 Financial Plan (Prorated)                         261,667.00                                          

Total Financial Plan Forecast                                            1,153,459.00

Proposed Contract Amount                                           1,795,200.00                                                                                                         

Variance (positive/ (negative))                              ($641,741.00)                       

 

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on November 8, 2023. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.