File #: 2025-221    Version: 1 Name:
Type: Resolution Status: New Business
File created: 6/30/2025 In control: Operations and Resources Committee
On agenda: 7/9/2025 Final action:
Title: Requisition No. REQ-0001651 Study and Design Services for the Pilot Netting and Disinfection Facilities at B-03, B-04, and B-05 CIP #270001/BCE Score: 89.6
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Attachments: 1. REQ-0001651.Procurement Board Report, 2. Req-0001651.Cost Tabulation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Requisition No. REQ-0001651

Study and Design Services for the Pilot Netting and Disinfection Facilities at B-03, B-04, and B-05

CIP #270001/BCE Score: 89.6

 

Body                     

Agenda of:                     July 23, 2025

Item No.:                     2025-221

Amount:                     $12,100,000.00

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     June 30, 2025

 

RE:                     Requisition No. REQ-0001651

                     Study and Design Services for the Pilot Netting and Disinfection Facilities at B-03, B-04, and B-05

                     Vendor:  Wade Trim Associates, Inc.

                     Status: New Contract/PO

 

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Requisition No. REQ-0001651, “Study and Design Services for the Pilot Netting and Disinfection Facilities at B-03, B-04, and B-05” with Wade Trim Associates, Inc., at a cost not to exceed $12,100,000.00 for a duration of 3,100 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

The 2020 GLWA Wastewater Master Plan Phase No. 1 recommends implementing pilot netting and disinfection facilities at four candidate locations. Netting and disinfection facilities remove floatables, trash, and debris and meets one of the nine minimum controls dictated by the United States Environmental Protection Agency Combined Sewer Overflow (CSO) Control Policy. GLWA does not currently utilize netting facilities and determined that a pilot project would be beneficial to determine the optimal netting configuration for GLWA’s operational requirements, also allows GLWA to monitor the operations and maintenance demand for this type of facility. Upon completion of the 2020 Wastewater Master Plan, GLWA was in discussion with the Michigan Department of Transportation (MDOT) concerning the I-94 Modernization Project. As part of the I-94 Modernization Project, Package No. 1 Drainage Agreement, MDOT agreed to provide design and construction funding for netting and disinfection facilities for three uncontrolled combined sewer outfalls downstream of the I-94 drainage system.

JUSTIFICATION

GLWA completed a Qualifications Based Selection (QBS) for the study, design, and construction administration for three CSO outfall netting facilities, B-03, B-04, and B-05, located between East Grand Boulevard and Water Works Park. The Engineer will investigate various alternatives to provide disinfection, netting, sampling, and odor control for these outfalls. The project will be carried out in accordance with the MDOT funding requirements.                     

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.              

Funding Source: 5421 - Wastewater Construction Fund

Cost Center: 880000 - Capital Improvement Program

Spend Category: Construction: Contractual Engineering

Project Worktag: PRJ-270001

Estimated Cost by Year and Related Estimating Variance: See table below.

Fiscal Year                                                             

FY26                                                                                             $983,000.00

FY27                                                                                               983,000.00

FY28                                                                                               985,000.00

FY29                                                                                            1,068,000.00

FY30                                                                                                                                                                            1,150,000.00

FY31+                                                                                                                                                                  3,453,000.00

Financial Plan Estimate                                                                 $8,622,000.00

Proposed Contract Award                                                         $12,100,000.00

Estimating Variance                                                                   ($3,478,000.00)

The award of this Contract to the vendor creates a negative estimating variance of $3,478,000.00. This variance will be funded from capital reserves.  

 

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on July 9, 2025.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.