Great Lakes Water Authority Logo
File #: 2023-463    Version: 1 Name:
Type: Resolution Status: Passed
File created: 11/29/2023 In control: Board of Directors Workshop Meeting
On agenda: 12/13/2023 Final action: 12/13/2023
Title: Proposed Amendment No. 4 Contract No. 1802448 Engineering Services for the 14 Mile Transmission Main Loop CIP #122013 / BCE Score: 58.4
Sponsors: Cheryl Porter
Indexes: Water Operations

Title

Proposed Amendment No. 4

Contract No. 1802448

Engineering Services for the 14 Mile Transmission Main Loop

CIP #122013 / BCE Score: 58.4

 

Body

Agenda of:                     December 13, 2023

Item No.:                     2023-463

Amount:                     Original Contract                                                                 $6,819,890.00

                                          Amendment No. 1                                                                   1,150,000.00

                                          Amendment No. 2                                                                   1,662,726.00

                                          Amendment No. 3                                                                      250,000.00

                                          Proposed Amendment No. 4                            145,366.00

                                          Total Revised Contract                                          $10,027,982.00

 

TO:                                          The Honorable

                                          Board of Directors

                                          Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                                          Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     December 1, 2023

 

RE:                                          Proposed Amendment No. 4

                                          Contract No. 1802448

                                          Engineering Services for the 14 Mile Transmission Main Loop

                                          Vendor:  Brown and Caldwell, LLC

 

 

MOTION

Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1802448, Proposed Amendment No. 4, “Engineering Services for the 14 Mile Transmission Main Loop” with Brown and Caldwell, LLC, at an increased cost of $145,366.00 for a total cost not to exceed $10,027,982.00, with no increase in duration for a total duration of 2,132 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

Contract No. 1802448 is an engineering contract involving design, bid, construction administration, and resident project representation (RPR) for construction of redundant and parallel transmission mains to provide redundancy for the communities serviced by the existing 14 Mile transmission main. The existing 14 Mile transmission main is a single line that supplies drinking water to the communities of Novi, Farmington Hills, West Bloomfield, Commerce, Walled Lake, and Wixom. If a disruption to service occurs on the 14 Mile Road transmission main (e.g., air valve break, blow-off valve break, water main break), then these communities will experience substantial loss in water pressure or complete loss of supply depending on the severity of the disruption. Therefore, GLWA launched this capital improvement program (CIP) project to provide new transmission main that connects the 14 Mile Road and 8 Mile Road transmission systems together, and a new parallel transmission main along 14 Mile Road west of M-5. The interconnection or “loop” between the 8 Mile Road and 14 Mile Road transmission systems along with the new parallel main west of M-5, when completed, will provide redundancy to the 14 Mile Road transmission main.

The engineering services contract for this CIP project was awarded to Brown and Caldwell in February 2019. This engineering services contract includes provisions to deliver the construction in two phases, as follows:

                     Phase I involves installing approximately 1.0 mile of 24-inch transmission along 14 Mile Road from M-5 to Decker Road. The GLWA Board awarded the construction contract (Contract No. 1903312) to Major Cement Company in May of 2020.

                     Phase II involves installing approximately 7.5 miles of 54-inch transmission main loop between 8 Mile Road and 14 Mile Road. The GLWA Board awarded the construction contract (Contract No. 2004456) to Ric-Man/Clark, a Joint Venture in October of 2021.

Amendment No. 1 was for additional funds for final design, RPR, project coordination, and utility survey.  Amendment No. 2 was for additional funds for construction assistance, RPR and an extension of 12 months to the final completion date.  Amendment No. 3 was for additional funds for Provisional Allowance.

Proposed Amendment No. 4 is requesting $145,366.00 to be added to Task 7- Construction Assistance to support the required additional time to complete the remaining Phase II construction. Phase II construction is scheduled to end August 30, 2024. This is due to coordination and constraints with working in the City of Novi regarding paving and final restoration.

 

JUSTIFICATION

The 14 Mile Transmission Main Loop Project constitutes a major capital investment towards providing redundancy to the 14 Mile Transmission System to avoid future catastrophic loss of service to the communities served by this transmission system. The remaining amount of the Construction Assistance is not sufficient to provide engineering services for the remaining of the Phase II construction contract.  The funds requested will allow additional Construction Assistance support during this complex construction project.

PROJECT MANAGEMENT STATUS

Original Contract Time                                           1,767 days                     (03/12/2019) - (01/12/2024)

Amendment No. 1                                                                      0 days

Amendment No. 2                                                                  365 days                      (01/13/2024) - (01/12/2025)

Amendment No. 3                                                                      0 days

Proposed Amendment No. 4                            0 days

New Contract Time                                                               2,132 days                     (03/12/2019) - (01/12/2025)

PROJECT ESTIMATE

Original Contract Price                                           $6,819,890.00

Amendment No. 1                                                       1,150,000.00

Amendment No. 2                                                       1,662,726.00

Amendment No. 3                                                                    250,000.00

Proposed Amendment No. 4              145,366.00

New Contract Total                                                    $10,027,982.00

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.          

Funding Source: Water Construction Bond

Cost Center: Field Engineering

Expense Type: Construction (5519-882111.000-617950-122013)

Estimated Cost by Year and Related Estimating Variance:  See table below.

Original Contract Price                                                                                    $6,819,890.00

Amendment No. 1                                                                                                           1,150,000.00

Amendment No. 2                                                                                                           1,662,726.00

Amendment No. 3                                                                                                              250,000.00

Proposed Amendment No. 4                                                                    145,366.00

New Contract Total                                                                                                         10,027,982.00

Amended Financial Plan Estimate                                            9,882,000.00

Negative Estimating Variance                                                    ($  145,982.00)

The award of this amendment to the vendor creates a negative estimating variance of $145,982.00. This variance will be funded from capital reserves.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on December 13, 2023. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.