Title: Proposed Change Order No. 1 Contract No. PO-1005275 (Former Emergency- REQ-0005499) Lake Huron WTP Flocculator Improvements CIP #111012 / BCE Score: N/A
Sponsors: Cheryl Porter
Indexes: Water Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Proposed Change Order No. 1

Contract No. PO-1005275 (Former Emergency- REQ-0005499)

Lake Huron WTP Flocculator Improvements

CIP #111012 / BCE Score: N/A

                     

Body

Agenda of:                     July 22, 2026

Item No.:                     2026-263

Amount:                     Original Contract Amount:                                          $2,102,806.96

                                          Proposed Change Order No. 1                     0.00

                                          Total Contract Amount                                          $2,102,806.96

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     June 30, 2026

 

RE:                     Proposed Change Order No. 1

                     Contract No.  PO-1005275

                     Lake Huron WTP Flocculator Improvements

                     Vendor: Philadelphia Mixing Solutions, LLC

                     Status: Amendment/Change Order

 

 

MOTION

Upon recommendation of  Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. PO-1005275, Proposed Change Order No. 1 “Lake Huron WTP Flocculator Improvements” with Philadelphia Mixing Solutions, LLC, at a cost not to exceed $2,102,806.96 for an increased duration of 123 days for a total duration of 487 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

GLWA issued Emergency PO-1005275 for direct purchase of rapid mix equipment for the Lake Huron Water Treatment Plant (LHWTP). GLWA elected to direct purchase this equipment to expedite its delivery and installation to meet an agreement with the Michigan Department of Environment, Great Lakes, and Energy (EGLE) to provide an increased velocity gradient in the rapid mixing process at the LHWTP. This PO supplies mixing equipment, motors, local starters, and variable frequency drives (VFDs); all equipment except the VFDs were to be provided on an expedited basis. The rapid mixers can be operated without the VFDs, allowing GLWA to meet its agreement with EGLE while the VFDs are delivered and installed after initial equipment commissioning.

JUSTIFICATION

This Proposed Change Order to PO-1005275 is a no-cost time extension. Due to supply chain delays, the VFDs are anticipated to be shipped after the current expiration date of the PO. While GLWA has taken steps to expedite submittal review and proactively address supplier delays, the supplier will not be able to meet their proposed delivery dates. This time extension provides for additional review of VFD submittal drawings, equipment fabrication, and equipment delivery. The supplier has committed to a reduction in the VFD lead-time from 22 weeks to 17 weeks following release to manufacture. Extending the PO will facilitate delivery of the equipment in line with the latest supplier schedule.                      

 

PROJECT MANAGEMENT STATUS

Original Contract Time                                            364 days (08/01/2025 - 07/31/2026)

Proposed Change Order No. 1                       123 days (08/01/2026 - 12/01/2026)                     

New Contract Time                                                                 487 days (08/01/2025 - 12/01/2026)

 

PROJECT ESTIMATE

Original Contract Price                                            $2,102,806.96

Proposed Change Order No. 1                                       0.00

New Contract Total                                                                 $2,102,806.96

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.          

Funding Source: 5519 - Water Construction Fund

Cost Center: 880000 - Capital Improvement Fund

Expense Type: 616900 - Construction

Project: 111012

Estimated Cost by Year and Related Estimating Variance: N/A

This proposed amendment is for an extension of time only. Although the amendment extends the final completion date further into FY 2027, there is no substantive financial impact.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on July 8, 2026.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.