File #: 2025-195    Version: 1 Name:
Type: Resolution Status: New Business
File created: 6/5/2025 In control: Operations and Resources Committee
On agenda: 6/11/2025 Final action:
Title: Proposed Amendment No. 1 Contract No. 2101475/SCN-0000439 CSO Facilities Improvements CIP #270004/BCE Score: 79.40
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Proposed Amendment No. 1

Contract No. 2101475/SCN-0000439

CSO Facilities Improvements

CIP #270004/BCE Score: 79.40

 

Body                     

Agenda of:                     June 25, 2025

Item No.:                     2025-195

Amount:                     Original Contract                                                                                                         $8,621,187.00

                                          Proposed Amendment No. 1                                                                 2,672,729.00

                                          Total Contract Amount                                                                        $11,293,916.00

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     June 5, 2025

 

RE:                     Contract No.  2101475/SCN-0000439

                     CSO Facilities Improvements

                     Vendor:  CDM Smith Michigan, Inc.

                     Status: Amendment/Change Order

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2101475/SCN-0000439, Proposed Amendment No. 1, “CSO Facilities Improvements” with CDM Smith Michigan, Inc., with an increased cost of $2,672,729.00 for a total cost not to exceed $11,293,916.00 and an increased duration of 1,147 days for a total duration of 3,575 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

GLWA awarded Contract No. 2101475 “CSO Facilities Improvements” to CDM Smith Michigan, Inc. (Engineer). The Contract is an Engineering Design Services Agreement for improvements to the Oakwood and Leib facilities, including storm pump modifications and wet well flushing system modifications at Oakwood, screen rehabilitation and replacement at Leib, and complete replacement of the chemical feed systems at both facilities. 

The improvements are needed in response to the wastewater masterplan’s planned projects which will more fully utilize these facilities up to their design capacities (maximizing existing infrastructure to control combined sewer overflow) by flow diversion.  Two of these projects that will divert flow include the active construction project to divert flow from the Northwest Interceptor (NWI) to the Oakwood CSO Facility and the in-development engineering contract to divert flow from the Meldrum sewer to the Leib Screening and Disinfection Facility.

This project has been approved for funding by the Michigan Department of Environment, Great Lakes, and Energy (EGLE) from the State Revolving Fund.

JUSTIFICATION

The original design contract included construction administration support for approximately 3-1/2 years.  The final design and construction phasing resulted in a 6-1/2 year construction window.  The increase in time is a result of enhanced project phasing to maintain permit compliance, additional manufacturing time beyond original assumptions, and more complex construction requirements to maintain hydraulic capacity within the facility after the upgrades are complete.

The increase in costs is a result of the increased construction duration and more complex construction.  The final costs are a result of negotiations, and it was confirmed that the staffing is in line with the original contract assumptions and reasonable staffing assumptions as needed to support the project through the end of construction.

PROJECT MANAGEMENT STATUS

Original Contract Time                                            2,428 days (09/16/2022 - 05/10/2029)

Proposed Amendment No. 1                      1,147 days (05/11/2029 - 06/30/2032)

New Contract Time                                                                 3,575 days (09/16/2022 - 06/30/2032)

 

 

PROJECT ESTIMATE

Original Contract Price                                             $8,621,187.00

Proposed Amendment No. 1                           2,672,729.00

New Contract Total                                                      $11,293,916.00

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.              

Funding Source: 5421 - Wastewater Construction Fund

Cost Center: 880000 - Capital Improvement Program

Spend Category: Construction: Contractual Engineering Services

Project Worktag: PRJ-270004

Estimated Cost by Year and Related Estimating Variance: See table below.

 Original Contract Price                                                                                     $8,621,187.00

Proposed Amendment No. 1                                                                  2,672,729.00

New Contract Total                                                                                                                                                $11,293,916.00

Amended Financial Plan Estimate                                            8,700,000.00

Balance reserved for construction:                                        ($2,593,916.00)

The award of this Contract to the vendor creates a negative estimating variance of $2,593,916.00. This variance will be funded from capital reserves.  

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on June 11, 2025.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.