Title: Proposed Change Order No. 2 Contract No. 2103688/SCN-0000204 Rehabilitation of Connors Creek Sewer System CIP# 260204/BCE Score: 78.30
Sponsors: Navid Mehram
Indexes: Wastewater Operations

Title

Proposed Change Order No. 2

Contract No. 2103688/SCN-0000204

Rehabilitation of Connors Creek Sewer System

CIP# 260204/BCE Score: 78.30

 

Body                     

Agenda of:                     February 25, 2026

Item No.:                     2026-045

Amount:                     Original Contract Amount                                                               $49,576,196.00

                                          Change Order No.1                                                                                                      0.00

                                          Proposed Change Order No. 2                                                                      0.00

                                          Contract Total                                                                                    $49,576,196.00

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     January 30, 2026

 

RE:                     Proposed Change Order No. 2

                     Contract No.  2103688/SCN-0000204

                     Rehabilitation of Connors Creek Sewer System

                     Vendor:  Oscar Renda Contracting, Inc.

                     Status: Amendment/Change Order

 

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2103688/SCN-0000204, Proposed Change Order No. 2 “Rehabilitation of Connors Creek Sewer System” with Oscar Renda Contracting, Inc., with no increase in cost for a cost not to exceed $49,576,196.00 and an increased duration of 127 days for a total duration of 1,611 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

The Connors Creek Sewer System (CCSS) starts at 8 Mile Road and ends south of Jefferson at the Conner Creek CSO (Combined Sewer Overflow) basin.  The interceptor ranges in size from 48” at it’s beginning to approximately 20 feet high x 65 feet wide at the CSO basin. The CCSS traverses along Outer Drive and Conner Street, under Mt. Olivet Cemetery, and Coleman Young City Airport, before reaching the “triple barrel” where it connects the Freud and Conner Pump Stations to the Conner Creek CSO Facility.  The total length of the CCSS is over 60,000 linear feet (over 11 miles).  CCSS is a combined sewer with a large water shed that is influenced greatly by rain and snowmelt (also known as wet weather).

Oscar Renda Contracting successfully completed its initial scope, well under budget. GLWA Engineering, through collaboration with Operations and Maintenance, identified cost effective opportunities to enhance the system under the existing contract, including additional improvements where the CCSS and the Conner Creek CSO Facility meet, as well as additional rehabilitation work to the CCSS under the Coleman A. Young Airport.

JUSTIFICATION

This extension in time is necessary to allow for the complex coordination and sequencing around Coleman A. Young Airport operations work on the CCSS, and around wet weather for the work in the basin entry bay near the Conner Creek CSO Facility. 

The base contract timeline was established based on time to clean the CCSS and not perform this type of highly coordinated and complex work scope at the airport and just upstream of the Conner Creek CSO Basin. This no-cost Change Order will extend the Substantial and Final completion dates through the end of 2026.                       

 

PROJECT MANAGEMENT STATUS

Original Contract Time                                            841 days (10/03/2022 - 01/20/2025)

Change Order No. 1                                           643 days (01/21/2025 - 10/25/2026)

Proposed Change Order No. 2                       127 days (10/25/2026 - 03/01/2027)

New Contract Time                                                    1,611 days (10/03/2022 - 03/01/2027)

PROJECT ESTIMATE

Original Contract Price                                            $49,576,196.00

Change Order No. 1                                                                        0.00

Proposed Change Order No. 2                                                  0.00

New Contract Total                                                                 $49,576,196.00

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.           

Funding Source: 5421 - Wastewater Construction Fund

Cost Center: 880000 - Capital Improvement Program

Spend Category: Construction 

Project Worktag: PRJ-260204

Estimated Cost by Year and Related Estimating Variance: See table below.

Original Contract Price                                                                           $49,576,196.00

Change Order No. 1                                                                                                       0.00

Proposed Change Order No. 2                                                                                  0.00

New Contract Total                                                                                                            49,576,196.00

Amended Financial Plan Estimate                                             49,576,196.00

Estimating Variance                                                                                                                $0.00 

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on February 11, 2026. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.