File #: 2021-476    Version: 1 Name:
Type: Resolution Status: Passed
File created: 12/1/2021 In control: Board of Directors Workshop Meeting
On agenda: 12/8/2021 Final action: 12/8/2021
Title: Contract No. 2100136 Pipe Hanger Replacement at Hubbell-Southfield CSO Facility O&M
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Attachments: 1. 2100136.Procurement Board Report-RFB, 2. 2100136.Cost Tabulation - Notice of Respondents

Title

Contract No. 2100136

Pipe Hanger Replacement at Hubbell-Southfield CSO Facility

O&M

 

Body                     

Agenda of:                     December 8, 2021

Item No:                     2021-476

Amount:                     $1,642,510.00

 

TO:                     The Honorable

                     Board of Directors

Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

Interim Chief Executive Officer

Great Lakes Water Authority

 

DATE:                     December 1, 2021

 

RE:                     Contract No. 2100136

                     Pipe Hanger Replacement at Hubbell-Southfield CSO Facility

                     Vendor: Weiss Construction Co., LLC

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA) authorizes the Interim Chief Executive Officer (ICEO) to enter into Contract No. 2100136, “Pipe Hanger Replacement at Hubbell-Southfield CSO Facility” with Weiss Construction Co., LLC at a cost not to exceed $1,642,510.00 for a duration of 548 days; and authorizes the ICEO to take such other action as may be necessary to accomplish the intent of this vote. 

 

 

 

BACKGROUND


Hubbell-Southfield CSO was built in 1994 under PC-694. Overhead piping in the basin was constructed using carbon or galvanized steel piping hangers. Due to damp conditions in the basin, as well as the continual presence of chloride (from CSO disinfection) and hydrogen sulfide (commonly present in sewer gases), these hangers have corroded to the point of imminent failure. In fact, a few locations have failed and were repaired as an emergency earlier in 2021. This project seeks to replace the failed hangers with new stainless-steel hangers, which will resist corrosion and are made of an appropriate material for the installation.

JUSTIFICATION

Failure of the piping hangers could result in a cascade failure (domino effect) of other nearby hangers that could cause failure of pipes. The previous pipe hanger failure affected the discharge sampling pump (a permit requirement) and a more serious/widespread failure could cause the basin to be taken out of service and will lead to violation of our NPDES permit and elimination of crucial basin systems, including dewatering/pumping, disinfection, and control gates. Additionally, and most importantly, these piping hanger failures represent a critical safety hazard for GLWA or other personnel entering and performing work in the basin, which occurs frequently.

FINANCIAL PLAN IMPACT

Summary:  The proposed project was not anticipated during the development of the Combined Sewer Overflow facilities budget. A budget amendment in the current year is anticipated. This is being evaluated on a prospective basis. This budget amendment will first be drawn from other budgeted areas, and secondly from the wastewater unallocated reserves.

Funding Source: Operations and Maintenance Budget (5960)

Cost Center:  Hubble Southfield Combined Sewer Overflow Facilities (892273)

Expense Type: Repairs & Maintenance - Facilities (622400)

Estimated Cost by Year and Related Forecast Variance:  See table below.

                     

                     FY 2022 Budget (Prorated)                                                                $18,710.00

                     FY 2023 Financial Plan                                                                             62,400.00

                     FY 2024 Financial Plan (Prorated)                                               5,230.00

                                          Financial Plan Forecast                                            $86,340.00

                     Maximum Contract                                                                                   1,642,510.00

                     Variance (positive/(negative))                        ($1,556,170.00)

 

 

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on December 8, 2021. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.