Great Lakes Water Authority Logo
File #: 2025-123    Version: 1 Name:
Type: Resolution Status: New Business
File created: 4/1/2025 In control: Board of Directors
On agenda: 4/23/2025 Final action:
Title: Proposed Amendment No. 1 Contract No. 2202790/SCN-0000382 WRRF Improvements to Sludge Feed Pumps at Dewatering Facilities CIP #213006/BCE Score: 76.60
Sponsors: Navid Mehram

Title

Proposed Amendment No. 1

Contract No. 2202790/SCN-0000382

WRRF Improvements to Sludge Feed Pumps at Dewatering Facilities

CIP #213006/BCE Score: 76.60

 

Body                     

Agenda of:                     April 23, 2025

Item No.:                     2025-123                                          

Amount:                     Original Contract                                                               $4,346,982.00                     

Proposed Amendment No. 1                            200,000.00

Total Contract Amount                                          $4,546,982.00                     

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     April 1, 2025

 

RE:                     Contract No.  2202790/SCN-0000382

                     WRRF Improvements to Sludge Feed Pumps at Dewatering Facilities

                     Vendor:  CDM Smith Michigan, Inc.

                     Status: Amendment/Change Order

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2202790/SCN No. 0000382, Proposed Amendment No. 1, “WRRF Improvements to Sludge Feed Pumps at Dewatering Facilities” with CDM Smith Michigan, Inc., with an increased cost of $200,000.00 for a total cost not to exceed $4,546,982.00 and no increase in duration for a total duration of 1,255 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

GLWA awarded Contract No. 2202790 “WRRF Improvements to the Sludge Feed System Pumps at Dewatering Facilities” to CDM Smith Michigan, Inc. (Engineer). The Contract is an Engineering Design services agreement for improvements to the Sludge Feed System, including replacing aged and improperly sized components, incorporating sludge feed loops into the conveyance systems, and providing improvements to the Sludge Storage Tank Pipe Gallery to mitigate future gallery flooding events.

JUSTIFICATION

The Contract includes a provisional allowance of $400,000.00 that has been utilized for design services to add improvements to the scope of work, such as electrical and control room improvements, identification and removal of previously abandoned infrastructure to eliminate obstructions and make it easier for our Operations and Maintenance Team to know what is and is not in service. This amendment will increase the allowance to facilitate immediate needs for State Revolving Fund funding documentation assistance, application for City of Detroit Building Permits, and to address any other future items as they arise throughout the completion of the design and the construction procurement effort.

PROJECT MANAGEMENT STATUS

Original Contract Time                                            1,255 days (4/14/2023 - 9/20/2026)

Proposed Amendment No. 1                                0 days                     

New Contract Time                                                                 1,255 days (4/14/2023 - 9/20/2026)

 

PROJECT ESTIMATE

Original Contract Price                                           $ 4,346,982.00

Proposed Amendment No. 1                             200,000.00

New Contract Total                                                                $ 4,546,982.00

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.              

Funding Source: 5421 - Wastewater Construction Fund

Cost Center: 880000 - Capital Improvement Program

Spend Category: Construction

Project Worktag: PRJ-213006

Estimated Cost by Year and Related Estimating Variance:  See table below.

 

Original Contract Price                                                              $4,346,982.00

Proposed Amendment No. 1                                                                                                     200,000.00

New Contract Total                                                                         $4,546,982.00

Amended Financial Plan Estimate                                          $16,000,000.00

Balance reserved for construction:                                          $11,453,018.00

 

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on April 10, 2025. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.