Title
Proposed Change Order No. 3
Contract No. 2102824/SCN-0000059
Rehabilitation of the Northwest Interceptor - 8 Mile Road to Tireman
CIP #260205/BCE Score: 60.3
Body
Agenda of: October 23, 2024
Item No.: 2024-317
Amount: Original Contract Price $6,934,703.00
Change Order No. 1 0.00
Change Order No. 2 938,152.35
Proposed Change Order No. 3 0.00
New Contract Total $7,872,855.35
TO: The Honorable
Board of Directors
Great Lakes Water Authority
FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority
DATE: September 26, 2024
RE: Proposed Change Order No. 3
Contract No. 2102824/SCN-0000059
Rehabilitation of the Northwest Interceptor - 8 Mile Road to Tireman
Vendor: LGC Global, Inc.
MOTION
Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2102824/SCN-0000059, Proposed Change Order No. 3, “Rehabilitation of the Northwest Interceptor - 8 Mile Road to Tireman” with LGC Global, Inc., with no increase in cost for a total cost not to exceed $7,872,855.35 and an increased duration of 366 days for a total duration of 1,189 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
The Northwest Interceptor conveyance system generally consists of pipes ranging in diameter from 4 feet to 13 feet and composed of numerous materials, including pre-cast concrete cylinders, cast-in-place concrete, brick, stone, and more. Conveyance projects typically have a few common elements among them, including cleaning and structural or maintenance type repairs followed by warranty inspections 1-year after the defects are repaired to ensure the repairs held. Minor pipe cleaning will occur through September 2024, and then the 1-year warranty inspection clock begins for the Northwest Interceptor Rehabilitation project.
JUSTIFICATION
Rehabilitation work is presently completed, and some cleaning work in the Northwest Interceptor reach between 8 Mile Road and Tireman will be completed in September 2024. To allow for this cleaning work, and for a 1-year warranty inspection to occur after all work is finalized, it is recommended to extend the contract end date.
PROJECT MANAGEMENT STATUS
Original Contract Time 631 days (07/01/2022 - 03/22/2024)
Change Order No.1 71 days (03/23/2024 - 06/01/2024)
Change Order No. 2 121 days (06/02/2024 - 09/30/2024)
Proposed Change Order No. 3 366 days (10/01/2024 - 10/01/2025)
New Contract Time 1,189 days (07/01/2022 - 10/01/2025)
PROJECT ESTIMATE
Original Contract Price $6,934,703.00
Change Order No. 1 0.00
Change Order No. 2 938,152.35
Proposed Change Order No. 3 0.00
New Contract Total $7,872,855.35
FINANCIAL PLAN IMPACT
Summary: Sufficient funds are provided in the financial plan for this project.
Funding Source: Wastewater Construction Fund
Cost Center: Wastewater Field Engineering
Expense Type: Construction (5421-892411.000-616900-260205)
Estimated Cost by Year and Related Estimating Variance: See table below.
Original Contract Price $6,934,703.00
Change Order No. 1 0.00
Change Order No. 2 938,152.35
Proposed Change Order No. 3 0.00
New Contract Total 7,872,855.35
Amended Financial Plan Estimate 6,935,000.00
Estimating Variance ($937,855.35)
This proposed change order is for an extension of time only and there is no substantive financial impact.
COMMITTEE REVIEW
This item was presented to the Operations and Resources Committee at its meeting on October 9, 2024. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.
SHARED SERVICES IMPACT
This item does not impact the shared services agreement between GLWA and DWSD.