File #: 2024-401    Version: 1 Name:
Type: Resolution Status: New Business
File created: 11/25/2024 In control: Operations and Resources Committee
On agenda: 12/11/2024 Final action:
Title: Proposed Amendment No. 5 Contract No. 1802543/SCN-0000063 Rehabilitation of Ferric Chloride Feed System at PS-1 and Complex B Sludge Lines CIP#211008/BCE Score: 78.3
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Proposed Amendment No. 5

Contract No. 1802543/SCN-0000063

Rehabilitation of Ferric Chloride Feed System at PS-1 and Complex B Sludge Lines

CIP#211008/BCE Score: 78.3

Body                     

Agenda of:                     December 11, 2024

Item No.:                     2024-401

Amount:                     Original Contract                                                                 $2,322,045.00

Amendment No. 1                                                                                0.00                                          

Amendment No. 2                                                                                          0.00

Amendment No. 3                                                            0.00

Amendment No. 4                                          0.00

Proposed Amendment No. 5                          0.00

Total Contract Amount                                           $2,322,045.00                                          

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     November 25, 2024

 

RE:                      Proposed Amendment No. 5

                     Contract No.  1802543/SCN-0000063

                                                 Rehabilitation of Ferric Chloride Feed System at PS-1 and Complex B Sludge Lines

                     Vendor:  Hazen and Sawyer

                     Status: Amendment/Change Order

                     

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1802543/SCN-0000063, Proposed Amendment No. 5, “Rehabilitation of Ferric Chloride Feed System at PS-1 and Complex B Sludge Lines” with Hazen and Sawyer, with no increase in cost for a total cost not to exceed $2,322,045.00 and an increased duration of 200 days for a total duration of 2,232 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

The main objective of the Hazen and Sawyer contract was to design a new Ferric Chloride feed system originating in Pump Station 2 (PS-2) and providing a feed of Ferric Chloride solution to existing Pump Station 1 (PS-1) via a new chemical feed system installed in the pipe gallery at the Water Resource Recovery Facility (WRRF).  Additionally, under this contract, Hazen and Sawyer was retained to develop a design to rehabilitate the existing thickened waste activated sludge line which conveys liquid sludge from Complex B to Complex A at the WRRF.  Further, the contract requires Hazen and Sawyer to provide construction phase engineering support, including reviews of the construction contractor’s submittals, responses to requests for information, development of as-built drawings, assistance in developing punch lists, and other services. The associated construction contract with this project (Contract No. 2002190) achieved final completion on August 30, 2024. However, while GLWA was preparing the documents to close out the Hazen and Sawyer contract (Contract No. 1802543), a leak was observed in the ferric chloride piping system during normal operations. Therefore, additional time is required to conduct a root cause analysis and produce revised drawings to address construction corrective work.

JUSTIFICATION

Time extension of the current consultant services Contract No. 1802543 held with Hazen and Sawyer is necessary to investigate and resolve the recently observed ferric chloride leak issues during normal operations. The leaks are suspected to stem from design deficiencies. To correct these issues, a root cause analysis will be conducted, followed by the preparation of the revised drawings and specifications. The Construction Contract for this project (Contract No. 2002190) reached final completion on August 30, 2024, and therefore, a determination on the methodology to complete the corrective construction work shall be made upon completion of the root cause analysis and revised drawings and specifications. In light of the above, GLWA Wastewater Engineering recommends extending the completion date of this Contract, with no increase in the contract amount.

 

 

 

PROJECT MANAGEMENT STATUS

 

Original Contract Time                                            976 days (05/22/2019 - 01/21/2022)

Amendment No. 1                                                                439 days (01/22/2022 - 04/05/2023)

Amendment No. 2                                                                244 days (04/06/2023 - 12/05/2023)

Amendment No. 3                                                                190 days (12/06/2023 - 06/12/2024)

Amendment No. 4                                                                183 days (06/13/2024 - 12/12/2024)

Proposed Amendment No. 5                      200 days (12/13/2024 - 06/30/2025)

New Contract Time                                                    2,232 days (05/22/2019 - 06/30/2025)                     

 

PROJECT ESTIMATE

Original Contract Price                                             $2,322,045.00

Amendment No. 1                                                                                              0.00

Amendment No. 2                                                                                           0.00

Amendment No. 3                                                                                           0.00

Amendment No. 4                                                                                           0.00

Proposed Amendment No. 5                                                 0.00                                                    

New Contract Total                                                                  $2,322,045.00

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.             

Funding Source: Sewer Construction Fund

Cost Center: Wastewater

Expense Type: Design (5421-892211.000-617950-211008)

Estimated Cost by Year and Related Estimating Variance:  See table below.

Original Contract Price:                                                          $2,322,045.00

Amendment No. 1                                                                                          0.00

Amendment No. 2                                                                                                                                                       0.00

Amendment No. 3                                                                                                                                                                 0.00

Amendment No. 4                                                                                                                                                                 0.00

Proposed Amendment No. 5                                                                $0.00 

New Contract Total:                                                                                                                   $2,322,045.00

Amended Financial Plan Estimate:                                        $2,322,045.00

Estimating Variance:                                                                              0.00

 

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on December 11, 2024.

 

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.