Title: Proposed Change Order No. 4 Contract No. 2004082 Rehabilitation of Woodward Sewer System CIP #260207/BCE Score: N/A
Sponsors: Navid Mehram
Indexes: Wastewater Operations

Title

Proposed Change Order No. 4

Contract No. 2004082

Rehabilitation of Woodward Sewer System                     

CIP #260207/BCE Score: N/A

 

Body

Agenda of:                      July 24, 2024

Item No.:                     2024-242

Amount:                     Original Contract Price                                          $18,695,250.00

                                          Change Order No.1                                                                                 0.00

                                          Change Order No. 2                                                  0.00

                                          Change Order No. 3                                                                      0.00

                                     Proposed Change Order No. 4                                                 0.00

                                          Contract Total                                                               $18,695,250.00                                                                                                                                                                                             

TO:                                          The Honorable

Board of Directors

Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                                          Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     July 16, 2024

 

RE:                                          Proposed Change Order No. 4

                     Contract No.  2004082

Rehabilitation of Woodward Sewer Systems

Vendor:  Lanzo Construction Co.

 

MOTION

 

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2004082, Proposed Change Order No. 4, “Rehabilitation of Woodward Sewer System” with Lanzo Construction Co., with no increase in cost for a total cost not to exceed $18,695,250.00 and an increased duration of 304 days for a total duration of 1,335 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

 

BACKGROUND

The Woodward Sewer System (WWSS) is a major combined sewer system aligned with Woodward Avenue starting at McNichols Road and conveys sewage through the cities of Highland Park and Detroit to the Detroit River Interceptor (DRI).  In addition, one leg of the WWSS extends sewer service to the east along Chandler and Clay streets and runs north into the city of Hamtramck.  This leg of the sewer, referred to as the WS-300 segment, consists of circular and egg-shaped brick sewers that are being rehabilitated by sliplining and Cured in Place Pipe (CIPP).

Change Order No. 1 extended the contract time for sliplining of the WS-300 sewer for extended material procurement time due to the pandemic and additional time for evaluation of potential substitutions.

Change Order No. 2 extended the key milestones for substantial and final completion dates by 42 days without liquidated damages. There was no change in contract value associated with this change order.

Change Order No. 3 extended the Contract time by 61 days with liquidated damages. There was no change in contract value associated with this change order.

JUSTIFICATION

This request is to extend the contract time of the project by 304 days with liquidated damages from August 1, 2024, to June 1, 2025. The contract time extension keeps the contract current past the final completion date, allowing for performance of the contract beyond final completion without interruption, if necessary, with GLWA reserving the right to assess liquidated damages for time beyond the key milestone of final completion which was June 1, 2024.

PROJECT MANAGEMENT STATUS

Original Contract Time                                           547 days (10/06/2021) - (04/05/2023)

Change Order No. 1                                          270 days (04/06/2023) - (12/31/2023)

Change Order No. 2                                          153 days (01/01/2024) - (06/01/2024)

Change Order No. 3                                   61 days (06/02/2024) - (08/01/2024)

Proposed Change Order No. 4     304 days (08/02/2024) - (06/01/2025)

New Contract Time                                                  1,335 days (10/06/2021) - (06/01/2025)

 

PROJECT ESTIMATE

Original Contract Price                                            $18,695,250.00

Change Order No. 1                                                                        0.00

Change Order No. 2                                                                       0.00                     

Change Order No. 3                                                                       0.00

Proposed Change No. 4                                  0.00

New Contract Total                                                                 $18,695,250.00

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.          

Funding Source: Wastewater Construction Fund

Cost Center: Wastewater Field Engineering

Expense Type: Construction (5421-892411.000-616900-260207)

Estimated Cost by Year and Related Estimating Variance:  See table below.

Original Contract Price                                                                        $18,695,250.00

Change Order No. 1                                                                                                    0.00

Change Order No. 2                                                                                                              0.00

Change Order No. 3                                                                                                                 0.00

Proposed Change Order No.4                                                                                         0.00

New Contract Total                                                                                                         18,695,250.00

Amended Financial Plan Estimate                                          18,695,250.00

Estimating Variance                                                                                           ($                0.00)

 

This proposed change order is for an extension of time only and there is no substantive financial impact.

COMMITTEE REVIEW

This item is being presented directly to the GLWA Board of Directors.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.