Skip to main content
Great Lakes Water Authority Logo
File #: 2026-031    Version: 1 Name:
Type: Resolution Status: New Business
File created: 1/30/2026 In control: Board of Directors
On agenda: 2/25/2026 Final action:
Title: Proposed Change Order No. 2 Contract No. 2003730/SCN-0000386 Water Transmission Main, Valve and Other Priority Repairs CIP #170504 / BEC Score: N/A
Sponsors: Cheryl Porter
Indexes: Water Operations

Title

Proposed Change Order No. 2

Contract No. 2003730/SCN-0000386

Water Transmission Main, Valve and Other Priority Repairs

CIP #170504 / BEC Score: N/A

 

Body

Agenda of:                     February 25,2026

Item No.:                     2026-031

Amount:                     Original Contract                                                               $15,000,000.00

                                          Change Order No.1                                                                 12,000,000.00

                                          Proposed Change Order No. 2                         2,000,000.00

                                          Contract Total                                                               $29,000,000.00

 

TO:                                          The Honorable

                                          Board of Directors

                                          Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                                          Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     January 30, 2026

 

RE:                                          Proposed Change Order No. 2

                                          Contract No. 2003730/SCN-0000386

                                          Water Transmission Main, Valve and Other Priority Repairs

                                          Vendor: LGC Global, Inc.

                                          Status: Amendment/Change Order

 

 

MOTION

Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2003730/SCN-0000386, Proposed Change Order No. 2, “Water Transmission Main, Valve and Other Priority Repairs” with LGC Global, Inc., for an increased cost of $2,000,000.00 for a total cost not to exceed $29,000,000.00 and no increase in duration for a total duration of five (5) years; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

 

BACKGROUND

The GLWA Water Transmission System consists of a network of approximately 800 miles of large (greater than 24-inch diameter) water mains that serve 3.8 million people across 115 communities that are represented by 88 member partners in eight (8) counties of southeastern Michigan. There are approximately 10,000 valves; air, blow-off, and isolation valves associated with these mains. The average pipe age is over 60 years old with some exceeding 150 years in age.

This contract is used to respond to water main breaks, valve repairs, and other urgent projects as necessary to allow GLWA to provide water of unquestionable quality at the promised level of service to our member partners. Contract No. 2003730 is one of two concurrent emergency repair contracts, the other being Contract No. 2301148 “Water Transmission Main, Valve and Other Priority Repairs,” that GLWA intends to maintain on a staggered basis. This contract will also support valve repairs determined from the Valve Exercising Program, Linear System Integrity Program, and the GLWA/DWSD water main decommissioning efforts.

Change Order No. 1 added additional funds to the Contract due to the 14 Mile Road Transmission Main rehabilitation from 2021.

JUSTIFICATION

The additional funds are being requested due to expenses associated with the 54-inch water main break on Beard Street in Southwest Detroit in February 2025 and the 42-inch water main break along 14 Mile Road in September 2025. The requested funds should allow this contract to be funded for the remaining contract term. This will allow the Contractor to continue to respond to urgent/emergencies within the system, provide support to our Linear System Integrity Program, and Decommissioning Program.

PROJECT MANAGEMENT STATUS

Original Contract Time                                           5 years (10/08/2021 - 10/7/2026)

Change Order No. 1                                           0 years

Proposed Change Order No. 2                     0 years

New Contract Time                                                                5 years (10/08/2021 - 10/7/2026)

 

 

 

PROJECT ESTIMATE

Original Contract Price                                           $15,000,000.00

Change Order No. 1                                             12,000,000.00

Proposed Change Order No. 2                         2,000,000.00

New Contract Total                                                                $29,000,000.00

FINANCIAL PLAN IMPACT

Summary: The proposed contract with Lakeshore Global Corporation encompasses Capital Improvement Plan & Operations & Maintenance expenses. The value of the contract exceeds the current financial plan in total. Potential positive variances of other contractual services as well as the use of this service may vary by year. Sufficient funds will be provided in the Operations & Maintenance (O&M) and CIP financial plan for this contract.

Funding Source: Operations & Maintenance (O&M) Budget, CIP 170504

Cost Centers: Field Service Operations - Centralized Services Cost Center (882431)

Expense Type(s): Contractual Operating Services - All Water (617901); Construction (616900)

CIP                                                O&M                                               Total

Original Contract Price                                          $10,000,000.00      $5,000,000.00      $15,000,000.00

Change Order No. 1                                               8,400,000.00        3,600.000.00        12,000,000.00

Proposed Change Order No. 2                            875,000.00        1,125,000.00          2,000,000.00

New Contract Total                                                                 19,275,000.00        9,725,000.00        29,000,000.00

Financial Plan Forecast                                            18,400,000.00        9,500,000.00        27,900,000.00

Estimating Variance                                                                  ($ 875,000.00)     ($ 225,000.00)      ($1,100,000.00)

The award of this change order provides an estimated O&M negative variance of ($225,000.00) and a CIP negative estimating variance of $875,000.00. A budget amendment will be necessary to record the estimating variance and will be funded from Program No. 170500. The CIP financial plan (forecast) is from the FY 2026-2030 CIP Plan. Contractual services are dependent on several factors such as delays in estimated start and end dates, environmental constraints, and other unforeseen circumstances that can cause the expenses to fluctuate from fiscal year to fiscal year.

COMMITTEE REVIEW