File #: 2025-179    Version: 1 Name:
Type: Resolution Status: New Business
File created: 5/30/2025 In control: Operations and Resources Committee
On agenda: 6/11/2025 Final action:
Title: Proposed Amendment No. 6 Contract No. 1802543/SCN-0000063 Rehabilitation of Ferric Chloride Feed System at PS-1 and Complex B Sludge Lines CIP #211008/BCE Score: 78.30
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Proposed Amendment No. 6

Contract No. 1802543/SCN-0000063

Rehabilitation of Ferric Chloride Feed System at PS-1 and Complex B Sludge Lines

CIP #211008/BCE Score: 78.30

 

Body                     

Agenda of:                     June 25, 2025

Item No.:                     2025-179

Amount:                     Original Contract                                                               $2,322,045.00

                                          Amendment No. 1                                                                               0.00

                                          Amendment No. 2                                                                               0.00

                                          Amendment No. 3                                                                                         0.00

                                          Amendment No. 4                                                                                         0.00

                                          Amendment No. 5                                                                               0.00

                                          Proposed Amendment No. 6                                               0.00

                                          Total Contract Amount                                          $2,322,045.00

                     

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     May 30, 2025

 

RE:                     Contract No.  1803542/SCN-0000063

                     Rehabilitation of Ferric Chlorie Feed System at PS-1 and Complex B Sludge Lines

                     Vendor:  Hazen & Sawyer

                     Status: Amendment/Change Order

 

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1803542/SCN-0000063, Proposed Amendment No. 6,  “Rehabilitation of Ferric Chloride Feed System at PS-1 and Complex B Sludge Lines” with Hazen & Sawyer with no increase in cost for a total cost not to exceed $2,322,045.00 and an increased duration of 183 days, for a total duration of 2,415 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

The main objective of the Hazen & Sawyer contract was to design a new Ferric Chloride feed system that allows operations to effectively manage the phosphorus that enters the plant. The final design optimized the system by originating the Ferric Chloride feed system in Pump Station 2 (PS-2) while also feeding PS-1 via a new chemical feed line installed in the pipe gallery at the Water Resource Recovery Facility.  Additionally, under this contract, Hazen & Sawyer was retained to develop a design to rehabilitate the existing SCB-30 thickened waste activated sludge (TWAS) line which conveys liquid sludge from Complex B to Complex A at the WRRF.  Further, the contract requires Hazen and Sawyer to provide construction phase engineering support, including reviews of the construction contractor’s submittals, responses to requests for information, development of as-built drawings, assistance in developing punch lists, and other services.

A leak in the ferric chloride piping system was observed in October 2024 during normal operations. The root cause of the leak was established, drawings were produced to address the issue, and a revised final pipe configuration was installed and tested. However, a temporary containment box was used to test the piping configuration, and the permanent containment box is yet to be delivered and installed. Therefore, Amendment No. 6 is required for Hazen & Sawyer’s work related to the delivery and installation of the permanent containment box. There are no associated costs for this work by Hazen & Sawyer.

JUSTIFICATION

A time extension of the current consultant services Contract No. 1802543 held with Hazen & Sawyer is necessary to allow for continuity of design and construction assistance by Hazen & Sawyer to completely resolve the ferric pipeline delivery issues described above. Therefore, GLWA Wastewater Operations recommends extending the Final Completion date, with no increase in the Contract amount.

                     PROJECT MANAGEMENT STATUS

Original Contract Time                                           976 days (05/22/2019 - 01/21/2022)

Amendment No. 1                                                                 439 days (01/22/2022 - 04/05/2023)

Amendment No. 2                                                               244 days (04/06/2023 - 12/05/2023)

Amendment No. 3                                                               190 days (12/06/2023 - 06/12/2024)

Amendment No. 4                                                               183 days (06/13/2024 - 12/12/2024)

Amendment No. 5                                                               200 days (12/13/2024 - 06/30/2025)

Proposed Amendment No. 6                     183 days (07/01/2025 - 12/31/2025)

New Contract Time                                                   2,415 days (05/22/2019 - 12/31/2025)

 

 

PROJECT ESTIMATE

Original Contract Price                                           $2,322,045.00

Amendment No. 1                                                                                          0.00

Amendment No. 2                                                                                         0.00

Amendment No. 3                                                                                         0.00

Amendment No. 4                                                                                         0.00

Amendment No. 5                                                                                         0.00

Proposed Amendment No. 6                                               0.00

New Contract Total                                                                $2,322,045.00

 

FINANCIAL PLAN IMPACT              

Funding Source: 5421 - Wastewater Construction Fund

Cost Center: 880000 - Capital Improvement Program

Spend Category: Construction: Contractual Engineering

Project Worktag: PRJ-211008

Estimated Cost by Year and Related Estimating Variance: See table below.

Original Contract                                                                                                         $2,322,045.00

Amendment No. 1                                                                                                                         0.00

Amendment No. 2                                                                                                                                                             0.00

Amendment No. 3                                                                                                                                   0.00

Amendment No. 4                                                                                                                                   0.00

Amendment No. 5                                                                                                                         0.00

Proposed Amendment No. 6                                                                                         0.00

New Contract Total                                                                                               $2,322,045.00

Amended Financial Plan Estimate                                            2,222,000.00

Estimating Variance                                                                  ($100,045.00)

The award of this Contract to the vendor creates a negative estimating variance of $100,045.00. This variance will be funded from capital reserves.  

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on June 11, 2025.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.