Great Lakes Water Authority Logo
File #: 2024-286    Version: 1 Name:
Type: Resolution Status: New Business
File created: 8/30/2024 In control: Board of Directors
On agenda: 9/25/2024 Final action:
Title: Proposed Amendment No. 3 Contract No. 2000970 Rehabilitation of Screened Final Effluent (SFE) Pump Station CIP# 216008/BCE Score: 63.2
Sponsors: Navid Mehram
Indexes: Wastewater Operations

Title

Proposed Amendment No. 3

Contract No. 2000970

Rehabilitation of Screened Final Effluent (SFE) Pump Station                     

CIP# 216008/BCE Score: 63.2

 

Body

Agenda of:                     September 25, 2024

Item No.:                     2024-286

Amount:                     Original Contract                                                                                     $3,399,730.00

                                          Amendment No. 1                                                                                         488,611.00

                                          Amendment No. 2                                                                                                              0.00

                                          Proposed Amendment No. 3                                                          0.00

                                          Total Contract Amount                                                               $3,888,341.00

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     August 30, 2024

 

RE:                                          Proposed Amendment No. 3

                     Contract No.  2000970

                     Rehabilitation of Screened Final Effluent (SFE) Pump Station

                     Vendor:  NORESCO, LLC

                     

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2000970, Proposed Amendment No. 3, “Rehabilitation of Screened Final Effluent (SFE) Pump Station” with NORESCO, LLC, with no increase in cost for a total cost not to exceed $3,888,341.00 and an increased duration of 182 days for a total duration of 1,457 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

GLWA awarded Contract No. 2000970 “Rehabilitation of Screened Final Effluent Pump Station to NORESCO LLC (Design/Build Contractor).  The contract is a progressive design build broken into two phases.  The first phase (current activities) includes alternative evaluations, basis of design report, 30% design, 60% design, and finally a lump sum price. The second phase will include completing design, construction, startup, commissioning, training, measurement/verification, and guaranteed savings (future amendment, anticipated 2025).

JUSTIFICATION

This proposed extension in the contract time for completion to March 31, 2025, will allow for the completion of negotiations surrounding the Phase 2 lump sum pricing agreement including the measurement and verification program to track energy and operations savings resulting from the facility.

 

PROJECT MANAGEMENT STATUS

Original Contract Time                                           1,052 days (04/05/2021 - 02/20/2024)

Amendment No. 1                                                                      0 days

Amendment No. 2                                                                  223 days (02/21/2024 - 09/30/2024)

Proposed Amendment No. 3                        182 days (10/01/2024 - 03/31/2025) 

New Contract Time                                                                1,457 days (04/05/2021 - 03/31/2025)

 

PROJECT ESTIMATE

Original Contract Price                                           $3,399,730.00

Amendment No. 1                                                                    488,611.00

Amendment No. 2                                                                                         0.00

Proposed Amendment No. 3                                               0.00

New Contract Total                                                                $3,888,341.00

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.          

Funding Source: Wastewater Construction Fund

Cost Center: Wastewater Field Engineering

Expense Type: Construction (5421-892211.000-616900-216008)

Estimated Cost by Year and Related Estimating Variance:  See table below.

Original Contract Price                                                                                    $3,399,730.00

Amendment No. 1                                                                                                             488,611.00

Amendment No. 2                                                                                                                                  0.00

Proposed Amendment No. 3                                                                                        0.00

New Contract Total                                                                                                        $ 3,888,341.00

Estimating Variance                                                                                                                                  0.00

This proposed change order is for an extension of time only and there is no substantive financial impact.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on September 11, 2024. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.