File #: 2026-044    Version: 1 Name:
Type: Resolution Status: New Business
File created: 1/30/2026 In control: Board of Directors
On agenda: 2/25/2026 Final action:
Title: Proposed Amendment No. 6 Contract No. 1802575/SCN-0000104 GLWA Conveyance System Engineering Services CIP #260204/BCE Score: 78.30
Sponsors: Navid Mehram
Indexes: Wastewater Operations

Title

Proposed Amendment No. 6

Contract No. 1802575/SCN-0000104

GLWA Conveyance System Engineering Services

CIP #260204/BCE Score: 78.30

 

Body                     

Agenda of:     February 25, 2026

Item No.:                     2026-044

Amount:                     Original Contract                                                                                    $3,149,897.00

                                          Amendment No. 1                                                                                                    0.00

                                          Amendment No. 2                                                                                      1,942,907.14

                                          Amendment No. 3                                                                                         382,004.00

                                          Amendment No. 4                                                                                      1,951,452.00

                                          Amendment No. 5                                                                                         938,027.95

                                               Proposed Amendment No. 6                                               496,920.00

                                               New Contract Total                                                                                    $8,861,208.09

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     January 30, 2026

 

RE:                     Proposed Amendment No. 6

                     Contract No.  1802575/SCN-0000104

                     GLWA Conveyance System Engineering Services

                     Vendor: Brown and Caldwell, LLC

                     Status: Amendment/Change Order

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1802575/SCN-0000104, Proposed Amendment No. 6 “GLWA Conveyance System Engineering Services” with Brown and Caldwell, LLC, at an increased cost of $496,920.00 for a total cost not to exceed $8,861,208.09 and an increased duration of 307 days for a total duration of 2,750 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

Collection System Engineering Services Contract No. 1802575 with Brown and Caldwell LLC (BC) covers engineering services for two (2) construction projects: the Connors Creek Sewer System (CCSS) Rehabilitation - GLWA Project No. 2103688, and the Woodward Sewer System (WWSS) Rehabilitation - GLWA Project No. 2004082.

The CCSS project successfully completed its scope, well under budget. GLWA Engineering, through collaboration with Operations and Maintenance, identified cost effective opportunities to enhance the CCSS system under the existing contract, including configuration to the structure where the CCSS and the Conner Creek Combined Sewer Overflow (CSO) Facility meet, as well as additional rehabilitation work to the CCSS under the Coleman A. Young Airport. This amendment will provide additional funds and a schedule extension for construction services to ensure compliance with the contract requirements.

The WWSS contract completion was delayed based on contractual issues with the original contractor. However, GLWA is in final resolution with the performance bond holder and anticipates the project completion in 2026 by another contractor under a performance bond claim. This amendment provides funds and a schedule extension for engineering and resident project representative services during construction.

 

JUSTIFICATION

This request for an amendment is for additional engineering scope and budget, and replenishment of a provisional allowance of $45,000.00. This will provide necessary construction administration services to support the very critical work in the CCSS under the airport runway and in the entering chamber at the Conner Creek CSO Facility to ensure compliance with the contract documents.  This additional work for the CCSS was completed within the original construction services budget.  However, an additional engineering budget for Brown & Caldwell is required for a greater level of support given the critical nature of the work in comparison with sewer cleaning and restoration. Additionally, in June 2024 the WWSS original construction contractor failed to complete their contractual obligation and demobilized. GLWA has brought a claim against their performance bond, requiring some additional engineering services from Brown & Caldwell to support the completion of the project and close out. 

This amendment is paired with a no cost change order for Oscar Renda Contracting for CCSS, and a contract to be executed for completing WWSS.

                     PROJECT MANAGEMENT STATUS

Original Contract Time                                            1,096 days (08/23/2019 - 08/22/2022)

Amendment No. 1                                                                       0 days

Amendment No. 2                                                                   731 days (08/23/2022 - 08/22/2024)

Amendment No. 3                                                                       0 days

Amendment No. 4                                                                   221 days (08/23/2024 - 03/31/2025)

Amendment No. 5                                                                   395 days (04/01/2025 - 04/30/2026)

Proposed Amendment No. 6                           307 days (05/01/2026 - 03/01/2027)

New Contract Time                                                                 2,750 days (08/23/2019 - 03/01/2027)

 

PROJECT ESTIMATE

Original Contract Price                                           $3,149,897.00

Amendment No. 1                                                                               0.00

Amendment No. 2                                                                 1,942,907.14

Amendment No. 3                                                                    382,004.00

Amendment No. 4                                                                 1,951,452.00

Amendment No. 5                                                                    938,027.95

Proposed Amendment No. 6                          496,920.00                                                                                                         

New Contract Total                                                                $8,861,208.09

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.

Funding Source: 5421 - Wastewater Construction Fund

Cost Center: 880000 - Wastewater Field Engineering

Spend Category: Construction: Contractual Engineering Services

Project Worktag: PRJ-260204 & PRJ-260207

Estimated Cost by Year and Related Estimating Variance: See table below.

Original Contract Price:                                                                                    $3,149,897.00

Amendment No. 1                                                                                                                                   0.00

Amendment No. 2                                                                                                           1,942,907.14

Amendment No. 3                                                                                                              382,004.00

Amendment No. 4                                                                                                           1,951,452.00

Amendment No. 5                                                                                                              938,027.95

Proposed Amendment No. 6                                                                    496,920.00 

New Contract Total:                                                                                                         $8,861,208.09

Amended Financial Plan Estimate:                                          $7,427,000.00

Estimating Variance:                                                                        ($1,434,208.06)

This proposed change order to the vendor creates a negative estimating variance of $1,434,208.06. This variance will be funded from capital reserves.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on February 11, 2026. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.