Skip to main content
Great Lakes Water Authority Logo
File #: 2026-138    Version: 1 Name:
Type: Resolution Status: New Business
File created: 4/1/2026 In control: Operations and Resources Committee
On agenda: 4/8/2026 Final action:
Title: Proposed Change Order No. 1 Requisition No. REQ-0007283/SCN-0000800 Emergency Construction Contract for Lake Huron Water Treatment Plant High Lift Building Column Repairs CIP #111009 / BCE Score: 75.70
Sponsors: Cheryl Porter
Indexes: Water Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Proposed Change Order No. 1

Requisition No. REQ-0007283/SCN-0000800

Emergency Construction Contract for Lake Huron Water Treatment Plant High Lift Building Column Repairs

CIP #111009 / BCE Score: 75.70

Body

Agenda of:                     April 22, 2026

Item No.:                     2026-138

Amount:                     Original Contract Price                                           $1,565,950.00

                                          Proposed Change Order No. 1                                     0.00

                                          Total Contract Amount                                          $1,565,950.00

 

TO:                                          The Honorable

                                          Board of Directors

                                          Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                                          Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     April 1, 2026

 

RE:                                          Requisition No. REQ-0007283/SCN-0000800

                                          Emergency Construction Contract for Lake Huron Water Treatment Plant High Lift Building Column Repairs

                                          Vendor: Pullman SST, Inc.

                                          Status: Amendment/Change Order

 

 

MOTION

Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Requisition No. REQ-0007283/SCN-0000800, Proposed Change Order No. 1, “Emergency Construction Contract for Lake Huron Water Treatment Plant High Lift Building Column Repairs” with Pullman SST, Inc., with no increase in cost for a total cost not to exceed $1,565,950.00 and an increased duration of 182 days for a total duration of 322 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

 

BACKGROUND

The Lake Huron Water Treatment Plant High Lift Building is constructed with post tensioning cables that are anchored to metal plates that are encased in concrete in the exterior columns. It was observed that the concrete caps were in deteriorated condition and had started to expose metal plates to the elements.  A repair detail to replace the concrete caps was developed through Contract No. 1803769 and construction was started through Contract No. 1803990.  Work was stopped during demolition when concrete degradation was discovered behind the bearing plates.  A revised design was developed through Contract No. 1803769.  The changed scope was not incorporated in Contract No. 1803990 due to the bonding company’s refusal to accept the change. There is an urgent need to complete repairs to avoid losing tension on the beams that would be a safety, structural and process risk and necessitate much more expensive repairs.

Due to the unseasonably cold weather, the Contractor could not perform repairs within the original schedule and took provisions to temporarily protect exposed columns. Additionally, there have been supply chain delays for the metal flashing.

JUSTIFICATION

The no-cost 182-day extension to SCN-0000800 is necessary for completion of these critical improvements.

PROJECT MANAGEMENT STATUS

Original Contract Time                                           140 days                     (11/12/2025 - 04/01/2026)

Proposed Change Order No. 1                     182 days                     (04/02/2026 - 09/30/2026)

New Contract Time                                                                322 days                     (11/12/2025 - 09/30/2026)

PROJECT ESTIMATE

Original Contract Price                                           $1,565,950.00

Proposed Change Order No. 1                                          0.00

New Contract Total                                                                $1,565,950.00

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.

Funding Source: 5519 - Water Construction Fund

Cost Center: 880000 - Capital Improvement Fund

Expense Type: 616900 - Construction

Estimated Cost by Year and Related Estimating Variance:  N/A

This proposed amendment is for an extension of time only. Although the amendment extends the final completion date into FY 2027, there is no substantive financial impact.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on April 8, 2026.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.