Title: Proposed Change Order No. 3 Contract No. 2002190 Rehabilitation of Ferric Chloride Feed Systems and Sludge Liner CIP #211008 / BCE Score: 78.3
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Proposed Change Order No. 3

Contract No. 2002190

Rehabilitation of Ferric Chloride Feed Systems and Sludge Liner

CIP #211008 / BCE Score: 78.3

 

Body

Agenda of:                     June 26, 2024

Item No.:                     2024-210

Amount:                     Original Contract                                                                                     $9,839,000.00

                      Change Order No. 1                                                           0.00

                      Change Order No. 2                                     300,000.00

                      Proposed Change Order No. 3                                0.00

                      Total Contract Amount                           $10,139,000.00

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     May 20, 2024

 

RE:                                          Proposed Change Order No. 3

                     Contract No.  2002190

                     Rehabilitation of Ferric Chloride Feed Systems and Sludge Lines

                     Vendor:  Weiss Construction Co., LLC

                     

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2002190, Proposed Change Order No. 3, “Rehabilitation of Ferric Chloride Feed Systems and Sludge Lines” with Weiss Construction Co., LLC, with no increase in cost for a total cost not to exceed $10,139,000.00 and an increased duration of 183 days for a total duration of 1,348 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

On April 5, 2021, GLWA issued the notice to proceed with Contract No. 2002190, to Weiss Construction Co., LLC.  The project is intended to improve reliability of the ferric chloride feed system at Pump Station No. 1 and the Thickened Waste Activated Sludge (TWAS) piping between Complex B and Complex A at the Water Resource Recovery Facility. The scope of work includes replacement of the existing ferric chloride feed system with new pumps and appurtenances, new ferric chloride storage tank and appurtenances, as well as modification and chemical cleaning of the TWAS pipeline from Complex B to Complex A.

The original agreement required substantial completion of the project on October 7, 2022, and final completion of the project on April 5, 2023.

The first two change orders added additional contractual time for completion of the work and added funds for unforeseen conditions encountered during construction.  Items resulting in delays included obtaining a permit from Conrail for the work beneath the train tracks and for additional time required to perform contractual cleaning of the TWAS pipe.

As of this letter, the TWAS line has been successfully cleaned and brought back into operation after many rounds of cleaning beyond what was originally anticipated. The current contractual substantial and final completion dates of the contract are June 8, 2023, and June 12, 2024.

JUSTIFICATION

Based on the status of the project, the project will not achieve the final completion milestone by June 12, 2024. There have been several factors attributed to delays in completion of the work, one major one being the multiple iterations of the TWAS cleaning effort. Additionally, final building inspection needs to be completed, deficiency items need to be resolved, miscellaneous site work, as well as the final closeout paperwork to follow. It is the GLWA’s engineering recommendation to extend the contract time at no additional cost to properly close out the project and complete the ongoing work.

 

 

 

 

 

 

 

 

PROJECT MANAGEMENT STATUS

Original Contract Time                                           731 days (04/05/2021 - 04/05/2023)

Change Order No. 1                                          244 days (04/06/2023 - 12/05/2023)

Change Order No. 2                                          190 days (12/06/2023 - 06/12/2024)

Proposed Change Order No. 3                     183 days (06/13/2024 - 12/12/2024)

New Contract Time                                                   1348 days (04/05/2021 - 12/12/2024)

 

PROJECT ESTIMATE

Original Contract Price                                           $9,639,000.00

Change Order No. 1                                                                    0.00

Change Order No. 2                                               300,000.00

Proposed Change Order No. 3                     0.00

New Contract Total                                                    $10,139,000.00

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.             

Funding Source: Sewer Construction Fund

Cost Center: Wastewater

Expense Type: Construction (5421-892211.000-616900-211008)

Estimated Cost by Year and Related Estimating Variance:  See table below.

Original Contract Price                      $9,839,000.00

Change Order No. 1:                                        0.00

Change Order No. 2:                                      300,000.00

Proposed Change Order No. 3:                                        0.00

New Contract Total:                     $10,139,000.00

Amended Financial Plan Estimate:                     $10,139,000.00

Estimating Variance:                     0.00

 

 

COMMITTEE REVIEW

This item is being presented directly to the GLWA Board of Directors.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.