Legislation Details

File #: 2026-218    Version: 1 Name:
Type: Resolution Status: New Business
File created: 6/3/2026 In control: Operations and Resources Committee
On agenda: 6/10/2026 Final action:
Title: Proposed Change Order No. 1 Contract No. 2403418/SCN-0000603 Emergency Baby Creek Chemical Tank Replacement CIP #260624
Sponsors: Navid Mehram, Christopher Nastally
Indexes: Wastewater Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Proposed Change Order No. 1

Contract No. 2403418/SCN-0000603

Emergency Baby Creek Chemical Tank Replacement

CIP #260624

 

Body                                          

Agenda of:                     June 25, 2026

Item No.:                     2026-218

Amount:                     Original Contract:                                                                                                          $3,159,000.00

Proposed Change Order No. 1                                                                                         0.00

Total Contract Amount:                                                                                    $3,159,000.00

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     June 3, 2026

 

RE:                                          Proposed Change Order No. 1

                     Contract No.  2403418/SCN-0000603

                     Emergency Baby Creek Chemical Tank Replacement

                     Vendor: FH Paschen S.N. Nielson and Associates, LLC

                     Status: Amendment/Change Order

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2403418/SCN-0000603, Proposed Change Order No. 1, with FH Paschen S.N. Nielson and Associates, LLC, with no increase in cost for a total cost not to exceed $3,159,000.00 for an increased duration of 169 Days for a total duration of 653 Days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.

BACKGROUND

GLWA awarded F.H. Paschen S.N. Nielson & Associates (FHP) a Construction Contract for the Emergency Baby Creek Chemical Tank Replacement Contract No. 2403418. The Notice to Proceed date was March 17, 2025. The purpose of the contract is to provide four (4) new chemical tanks and piping for the Baby Creek Screening and Disinfection Facility’s chemical feed system, demolish one old chemical storage tank, and provide new heating, ventilation, and air conditioning units. The contractual Substantial and Final Completion dates are March 17, 2026, and July 14, 2026, respectively.

The contractor encountered site specific challenges when loading the new chemical tanks for final assembly, which delayed overall progress. As a result, the project schedule was impacted, and based on the current rate of progress, the project is not likely to achieve either contract milestone by its contractual date.

Therefore, a contract time extension is necessary to ensure the project can be fully and properly closed out in accordance with contract requirements. The recommended time extension is 169 calendar days with no added cost to the project. GLWA reserves the right to assess Liquidated Damages against FHP should closeout requirements remain unsatisfied beyond the required Final Completion Date of July 14, 2026.

JUSTIFICATION

Based on the current rate of progress, the project will not achieve either of the contract milestones by their contractual date. Therefore, and to ensure that proper closeout procedure can take place within the contract time, additional time of 169 calendar days, extending the contract time, is recommended with no additional cost to GLWA.                     

PROJECT MANAGEMENT STATUS

                                              

Original Contract Time:                        485 days (03/17/2025 - 07/14/2026)

Proposed Change Order No.1             169 days (07/15/2026 - 12/31/2026)

New Contract Time:                                                  654 days (03/17/2025 - 12/31/2026)

 

PROJECT ESTIMATE

Original Contract Price                                           $3,159,000.00

Proposed Change Order No. 1                                                0.00

New Contract Total                                                                $3,159,000.00

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.              

Funding Source: 5421 - Wastewater Construction Fund

Cost Center: 880000 - Capital Improvement Program

Spend Category: Construction

Project Worktag: PRJ-260624

Estimated Cost by Year and Related Estimating Variance: See table below.

Original Contract Price                                                              $3,159,000.00

Proposed Change Order No. 1                                                                  0.00

New Contract Total                                                                         $3,159,000.00

Amended Financial Plan Estimate                                            $4,065,000.00

Estimating Variance:                                                                    $906,000.00

 

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on June 10, 2026.

 

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.