File #: 2023-302    Version: 1 Name:
Type: Resolution Status: Passed
File created: 8/1/2023 In control: Board of Directors
On agenda: 8/23/2023 Final action: 8/23/2023
Title: Proposed Change Order No. 4 Contract No. 1903598 Construction Manager at Risk for the Assessment and Rehabilitation of WRRF Yard Piping and Underground Utilities CIP #216006 / BCE Score: 79.0
Sponsors: Navid Mehram
Indexes: Wastewater Operations

Title

Proposed Change Order No. 4

Contract No. 1903598

Construction Manager at Risk for the Assessment and Rehabilitation of WRRF Yard Piping and Underground Utilities                     

CIP #216006 / BCE Score: 79.0

 

Body

Agenda of:                     August 23, 2023

Item No.:                     2023-302

Amount:                     Original Contract                                                                 $4,863,051.00

Change Order No. 1                                                  685,450.00

Change Order No. 2                                          596,779.00

Change Order No. 3                                                                         0.00

Proposed Change Order No. 4                         5,000,000.00

Total Revised Contract                                              $11,145,280.00

 

TO:                     The Honorable

Board of Directors

Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

Chief Executive Officer

Great Lakes Water Authority                     

 

DATE:                     August 1, 2023

 

RE:                                          Proposed Change Order No. 4

                     Contract No.:  1903598

Construction Manager at Risk for the Assessment and Rehabilitation of WRRF Yard Piping and Underground Utilities

                     Vendor: The Christman Company

 

MOTION

 

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1903598, Proposed Change Order No. 4, “Construction Manager at Risk for the Assessment and Rehabilitation of WRRF Yard Piping and Underground Utilities” with The Christman Company, at an increased cost of $5,000,000.00 for a total cost not to exceed $11,145,280.00 and an increased duration of 243 days for a total duration of 1,231 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.

BACKGROUND

 

GLWA awarded Contract No. 1903598 to The Christman Company (Construction Manager (CM)) with a start work date of January 15, 2021. This Contract is divided into several phases including (study, preliminary design, final design, and construction) for the piping at the Water Resource Recovery Facility. Through this construction delivery method, change orders are utilized as the funding method to support the progress of the project. As the packages are developed by the designer CDM Smith Michigan Contract No. 1903601 the CM proceeds with advertisement and award with collaboration with GLWA and Designer for execution.

Three Change Orders have been issued under this Contract. Change Order (CO) No.1 for additional condition assessment of the underground utilities, CO No. 2 increased funding for the preliminary and final design phases, and CO No. 3 extended the contract times for bidding and negotiation of the final design packages.

 

The contract continues to progress, and the improvement documents are approaching 75, 90, or 100% design.  Change Order No. 3 set a new completion date for the final design. However, unforeseen design changes and newly realized necessary scope additions pushed the final design to early July.  These are also documented in the parallel Amendment No. 4 for Contract No. 1903601, Yard Piping Engineering Services.  It is anticipated that four separate packages are necessary to successfully complete the recommended improvements, the first of which will be advertised in late August. The goal is to start construction on the first packages in the fall of 2023. 

 

The proposed Change Order No. 4 seeks to add money for advancement of key long lead items, abatement, and demolition while the bids are formalized into an overall recommendation for the GLWA Board of Directors’ approval.  Additionally, the extension in contract time is to allow adequate time in the construction contract to collect all bids and establish Guaranteed Maximum Price (GMP).

 

 

 

 

 

JUSTIFICATION

 

The request for funding is to support early engagement for key long lead item submittals, initiate abatement, and demolition to meet the current planned schedule. This advancement will allow for a seamless transition to the bid packages, minimizing future delays and reducing the escalation factor for key project items.  Other important lead time items may come out during the bidding process and this advance construction money will allow the GLWA Engineering, Designer, and Construction Manager at Risk (CMAR) team to move forward without delay as needed. GLWA intends to bring forth future change order when GMP has been established for the remaining packages.  

 

 

PROJECT MANAGEMENT STATUS

 

Original Contract time for Study/Design                                           792 days (01/15/2021 - 03/17/2023)

Change Order No. 1                                                                                          0 days

Change Order No. 2                                                                                         0 days

Change Order No. 3                                                                           197 days (03/18/2023 - 09/30/2023)

Proposed Change Order No. 4                                                      243 days (10/01/2023 - 05/30/2024)                     

New Contract Time                                                                                             1,232 days (01/15/2021 - 05/30/2024)

 

 

 

PROJECT ESTIMATE

 

Original Contract Price                                                                                                          $4,863,051.00

Change Order No. 1                                                                                                               685,450.00                     

Change Order No. 2                                                                                                                596,779.00

Change Order No. 3                                                                                                                                        0.00

Proposed Change Order No. 4                                                                                       5,000,000.00

New Contract Price                                                                                                $11,145,280.00

 

 

 

FINANCIAL PLAN IMPACT

 

Summary: Sufficient funds are provided in the financial plan for this project.             

Funding Source: Sewer Construction Fund

Cost Center: Wastewater

Expense Type: Construction (5421-892211.000-616900-216006)

Estimated Cost by Year and Related Estimating Variance:  See table below.

Original Contract Price:                                                            $4,863,051.00

Change Order No. 1:                                                                                                                       $685,450.00                     

Change Order No. 2                                                                                                                          596,779.00

Change Order No. 3                                                                                                                                                  0.00

Proposed Change Order No. 4:                                                                          $5,000,000.00

New Contract Total:                                                                                                        $11,145,280.00

Amended Financial Plan Estimate:                                          22,449,000.00

Balance reserved for construction:                                         $11,303,720.00

 

COMMITTEE REVIEW

 

This item was presented to the Operations and Resources Committee at its meeting on August 9, 2023. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

 

This item does not impact the shared services agreement between GLWA and DWSD.