Great Lakes Water Authority Logo
File #: 2023-202    Version: 1 Name:
Type: Resolution Status: Passed
File created: 5/23/2023 In control: Board of Directors
On agenda: 6/28/2023 Final action: 6/28/2023
Title: Contract No. 2300600 96-Inch Water Transmission Main Relocation - Phase II CIP #122004 / BCE Score: 77.5
Sponsors: Cheryl Porter
Indexes: Water Operations
Attachments: 1. 2300600 Procurement Board Report-RFB, 2. 2300600 Cost Tabulation - Notice of Respondents

Title

Contract No. 2300600

96-Inch Water Transmission Main Relocation - Phase II

CIP #122004 / BCE Score: 77.5

Body

Agenda of:                     June 28, 2023

Item No.:                     2023-202

Amount:                     $56,350,500.00

 

TO:                                          The Honorable

                                          Board of Directors

                                          Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                                          Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     May 26, 2023

 

RE:                                          Contract No. 2300600

                                          96-Inch Water Transmission Main Relocation - Phase II

                                          Vendor:  Ric-Man/Clark Joint Venture

 

 

MOTION

Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2300600, “96-Inch Water Transmission Main Relocation - Phase II” with Ric-Man/Clark Joint Venture, at a cost not to exceed $56,350,500.00 for a duration of 852 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

The existing 96-inch Water Transmission Main (WTM) is part of GLWA’s overall drinking water transmission main system that interconnects the Lake Huron Water Treatment Plant (LHWTP) with the Northeast and Springwells Water Treatment Plants (WTPs) through the North Service Center Pumping Station. The existing 96-inch WTM was constructed in the mid-1960s and was placed into service in December 1967. Part of the original construction of the 96-inch WTM was a section within Shelby Township that was installed within the influence of the G&H Industrial Landfill site.

The current relocation project consists of approximately 2.5 miles of 96-inch WTM currently located in the influence of the decommissioned G&H Industrial Landfill site, a listed U.S. Environmental Protection Agency Superfund Site located in Shelby Township, MI. The construction has been sequenced to occur in three phases as follows:

                     Phase I referred to as the “Early Works Package - Avon Road Improvements” consisted of 2,200 lineal feet of new 96-inch WTM to be installed along Avon Road in Rochester Hills. Phase I of construction is currently in progress under Contract No. 2004825 and is anticipated to be completed in Mid-August of 2023.

                     Phase II scope of work includes installation of 7,985 lineal feet of 96-inch WTM installation along Dequindre Road between Hamlin Road and the Macomb Orchard Trail just north of 23 Mile Road.

                     Phase III scope of work will include 2,900 lineal feet of 96-inch WTM installation along the Macomb Orchard Trail between Dequindre Road and 24 Mile Road. Phase III will include system isolation valves, final connections near the Rochester Booster Station and the intersection of Dequindre/Hamlin Road, and the abandonment of existing WTM.

Once all three phases are complete, the relocated 96-inch WTM will be connected to GLWA’s existing WTM system between the North Service Center and Rochester Booster Station. Upon placing the new section of 96-inch WTM into service, the existing WTM within the influence of the inactive G&H Industrial Landfill site will be decommissioned and abandoned in place.

JUSTIFICATION

Contract No. 2300600 is for Phase II of the 96-inch WTM relocation project. This project is considered a priority project under the Michigan Department of Environment, Great Lakes, and Energy (EGLE) Drinking Water State Revolving Fund (DWSRF).  In order to maintain the EGLE funding fiscal year loan schedule and priority status, approval of Contract No. 2300600 is required. The continuation of the 96-inch WTM relocation project is essential in providing improved access for future operations and maintenance of the 96-inch WTM.  In addition, it will increase resiliency of the water transmission main system with the installation of isolation valves allowing for operational flexibility and redundancy in the future.

 

 

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.

Funding Source: Water Construction Fund

Cost Center: Water Field Engineering

Expense Type: Construction (5519-882411.000-616900-122004)

Estimated Cost by Year and Related Estimating Variance:  See table below.

Fiscal Year

FY 2023 Plan                                                                                              $  36,851,000.00

FY 2024 Plan                                                                                                           82,005,000.00

FY 2025 Plan                                                                                                           55,112,000.00

FY 2026 Plan                                                                                                           17,332,000.00

FY 2027 Plan                                                                                                           17,332,000.00

FY 2028 Plan                                                                                                           19,741,000.00

FY 2029 - 2033 Plan                                                                                        3,086,000.00

Financial Plan Estimate                                                                        $231,459,000.00

   

Financial Plan Estimate                                                                        $231,459,000.00

   Less: Phase I Contracts Awarded

      Phase I Contract 2004825                                                                 36,342,500.00

      Phase I Contract 2100998                                                                   9,237,583.00

   Less: Phase II Contract Request

      Phase II Proposed Contract Award                                            56,350,500.00

Phase III Available Plan Estimate                                                   $129,528,417.00

 

 

 

 

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on June 14, 2023. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.