File #: 2023-256    Version: 1 Name:
Type: Resolution Status: Passed
File created: 6/29/2023 In control: Board of Directors
On agenda: 7/26/2023 Final action: 7/26/2023
Title: Proposed Amendment No. 4 Contract No. GLWA-CS-060 Study/Design of an Upgraded Sludge Conveyance System and Lighting Improvements at the Detroit Wastewater Treatment Plant CIP #213007 / BCE Score: N/A
Sponsors: Navid Mehram, Christopher Nastally
Indexes: Wastewater Operations

Title

Proposed Amendment No. 4

Contract No. GLWA-CS-060

Study/Design of an Upgraded Sludge Conveyance System and Lighting Improvements at the Detroit Wastewater Treatment Plant 

CIP #213007 / BCE Score: N/A

 

Body

Agenda of:                      July 26, 2023

Item No.:                     2023-256

Amount:                     Original Contract                     $1,990,000.00

Amendment No. 1                     96,404.00

Amendment No. 2                     0.00

Amendment No. 3                     0.00

Proposed Amendment No. 4                     0.00

                     Total Contract Amount               $2,086,404.00

                                                                                                                                                                                                                  

 

TO:                                          The Honorable

Board of Directors

Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                                          Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     June 29, 2023

 

 

RE:                                          Proposed Amendment No. 4

                     Contract No.:   GLWA-CS-060

Study/Design of an Upgraded Sludge Conveyance System and Lighting Improvements at the Detroit Wastewater Treatment Plant 

                                          Vendor: Black & Veatch Ltd. of Michigan

 

 

MOTION

 

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. GLWA-CS-060, Proposed Amendment No. 4, “Study/Design of an Upgraded Sludge Conveyance System and Lighting Improvements at the Detroit Wastewater Treatment Plant” with Black & Veatch Ltd. of Michigan, with no increase in cost for a total cost not to exceed $2,086,404.00 and for an increased duration of 215 days, for a total duration of 2,834 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

Black & Veatch Limited of Michigan was awarded the original contract to provide, study, design, and construction assistance to GLWA with a start work date of April 29, 2016. The main objective of the Black & Veatch consultant services contract was to restore sludge conveyance capacity lost due to the March 2016 fire damage while providing improved sludge conveyance from each dewatering facility to improve operations and minimize future risks.

On April 14, 2018, Black & Veatch was granted Amendment No. 1 for additional design and construction assistance activities.

On May 26, 2021, Black & Veatch was granted Amendment No. 2 to extend the contract time from June 30, 2021, to June 30, 2022, due to delays in the related construction contract, GLWA-CON-197, caused by unforeseen conditions and the COVID-19 pandemic.

On June 22, 2022, Black & Veatch was granted Amendment No. 3 to extend the contract time from July 1, 2022, to June 30, 2023, due to equipment performance issues that were delaying completion of the related construction contract, GLWA-CON-197.

JUSTIFICATION

Construction Amendment No. 3 was issued on February 3, 2023, to Weiss Construction Company for the associated construction contract (GLWA-CON-197) extending the construction contract times to March 30, 2023, for Substantial Completion and September 29, 2023, for final completion. Because of ongoing performance issues associated with some of the new equipment and other issues, GLWA-CON-197 has not yet achieved substantial completion and is not expected to achieve final completion by September 29, 2023.

Additionally, repeated strainer backwash piping leaks and conveyor drip pan spray issues have necessitated design revisions prolonging construction due to long-lead material deliveries and subsequent installation time.

GLWA Wastewater Engineering has assessed that a contract extension is needed for the current contract time under GLWA-CS-060. The extended final completion date will allow for Black & Veatch to complete the remaining contractual construction administration services to GLWA. No additional contract funding is required as a result of this time extension.

PROJECT MANAGEMENT STATUS

Original Contract Time                                              914 days (04/29/2016 - 10/29/2018)

Amendment No. 1                                                                       974 days (10/30/2018 - 06/29/2021)

Amendment No. 2                                                                       366 days (06/30/2021 - 06/30/2022)

Amendment No. 3                                                                       365 days (07/01/2022 - 06/30/2023)

Proposed Amendment No. 4                          215 days (07/01/2023 - 01/31/2024)

New Contract Time                                                                2,834 days (04/29/2016 - 01/31/2024)

 

PROJECT ESTIMATE

Original Contract Price                      $1,990,000.00

Amendment No. 1                     96,404.00

Amendment No. 2                     0.00

Amendment No. 3                     0.00

Proposed Amendment No. 4                      0.00

New Contract Total                      $2,086,404.00

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.             

Funding Source: Sewer Construction Fund

Cost Center: Wastewater

Expense Type: Design (5421-892211.000-617950-213007)

This is a time extension Amendment. There will be no financial impact.

 

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on July 12, 2023. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.