Legislation Details

File #: 2026-443    Version: 1 Name:
Type: Resolution Status: New Business
File created: 10/23/2026 In control: Operations and Resources Committee
On agenda: 11/12/2026 Final action:
Title: Requisition No. REQ-0008437 North Service Center Pumping Station Improvements CIP #132016 / BCE Score: 98.7
Sponsors: Cheryl Porter
Indexes: Water Operations
Attachments: 1. REQ-0008437 Procurement Board Report, 2. REQ-0008437 Cost Tabulation with Alternate
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Requisition No. REQ-0008437

North Service Center Pumping Station Improvements

CIP #132016 / BCE Score: 98.7

Body

Agenda of:                     November 19, 2026

Item No.:                     2026-443

Amount:                     $111,515,700.00

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     October 23, 2026

 

RE:                     Requisition No. REQ-0008437

                     North Service Center Pumping Station Improvements

                     Vendor: F.H. Paschen

                     Status: New Contract/PO

 

 

MOTION

Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Requisition No. REQ-0008437, “North Service Center Pumping Station Improvements” with F.H. Paschen, at a cost not to exceed $111,515,700.00 for a duration of 2,150 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

The North Service Center Pumping Station (North Service Center), located in Troy, Michigan, boosts water pressure from the Northeast Water Treatment Plant and Imlay Booster Pump Station (or Lake Huron Water Treatment Plant when Imlay is bypassed) to serve the entirety of or a portion of the following member communities: the cities of Auburn Hills, Bloomfield Hills, Farmington Hills, Keego Harbor, Novi, Pontiac, Rochester, Rochester Hills, Sylvan Lake, Troy, Walled Lake, and Wixom; the townships of Bloomfield, Commerce, Shelby, and West Bloomfield; and the Southeast Oakland County Water Authority (SOCWA). The existing pumping units, electrical distribution, and electrical switchgear equipment are near the end of their service life and are not providing reliable, efficient service. This project replaces six (6) pumping units, two (2) of three (3) switchgear lineups, five (5) motor control centers, and two (2) of four (4) variable frequency drives.  The project adds uninterruptible power supply to the pump discharge control valves and adds a bypass discharge main to allow for the pump station to remain in service for future planned transmission main maintenance activities. An isolation valve will be added on the 54-inch transmission main to allow for future transmission system improvements. This project also makes various structural and architectural improvements to extend the life of the existing pump station structure.

JUSTIFICATION

The existing station building and structure is useable with minor upgrades, and the station rehabilitation maximizes the use of the existing facility while replacing the necessary mechanical and electrical gear to meet the system demands of its service area projected through 2045. The mechanical and electrical equipment replacements will improve asset utilization, reduce maintenance costs and downtime, and improve asset reliability for Water Operations.

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.

Funding Source: 5519 - Water Construction Fund

Cost Center: 880000 - Capital Improvement Fund

Expense Type: 616900 - Construction

Project: 132016

Estimated Cost by Year and Related Estimating Variance: See table below.

Fiscal Year

FY 2027 Planned Spend                                                                                                         $   16,495,000.00

FY 2028 Planned Spend                                                                                                              28,320,000.00

FY 2029 Planned Spend                                                                                                              31,793,000.00

FY 2030 Planned Spend                                                                                                              23,705,000.00

FY 2031 Planned Spend                                                                                                                8,010,000.00

Financial Plan Estimate                                                                                                         $ 108,323,000.00

Proposed Contract Award                                                                                                            111,515,700.00

Estimating Variance                                                                                                                              $    (3,192,700.00)

Projects have been reallocated to account for the estimating variance.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on November 12, 2026.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.