File #: 2023-212    Version: 1 Name:
Type: Resolution Status: Passed
File created: 5/26/2023 In control: Board of Directors
On agenda: 6/28/2023 Final action: 6/28/2023
Title: Proposed Amendment No. 1 Contract No. 2000970 Rehabilitation of Screened Final Effluent (SFE) Pump Station CIP #216008/BCE Score: 63.2
Sponsors: Navid Mehram
Indexes: Wastewater Operations

Title

Proposed Amendment No. 1

Contract No. 2000970

Rehabilitation of Screened Final Effluent (SFE) Pump Station                     

CIP #216008/BCE Score: 63.2

 

Body

Agenda of:                     June 28, 2023

Item No.:                     2023-212

Amount:                     Original Contract Amount                                                               $3,399,730.00

                                          Proposed Amendment No. 1                                               488,611.00

                                          Total Revised Contract                                                               $3,888,341.00

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     May 26, 2023

 

RE:                                          Proposed Amendment No. 1

                     Contract No.:  2000970

                     Rehabilitation of Screened Final Effluent (SFE) Pump Station

                     Vendor:  NORESCO LLC

                     

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer- Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2000970, Proposed Amendment No. 1, “Rehabilitation of Screened Final Effluent (SFE) Pump Station” with NORESCO LLC, at an increased cost of $488,611.00 for a total cost not to exceed $3,888,341.00 with no increase in duration for a total duration of 1,052 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

GLWA awarded Contract No. 2000970 “Rehabilitation of Screened Final Effluent (SFE) Pump Station” to NORESCO LLC (Design/Build Contractor), with a start work date of April 5, 2021. The Contract is a progressive design build broken into two phases. The first phase (current activities) includes alternative evaluations, basis of design report, 30% design, 60% design and finally a lump sum price and cost savings.  The second phase will include completing design, construction, startup, commissioning, training, measurement/verification, and guaranteed savings (future amendment, anticipated late 2023).  

Under Task 2 Alternative Evaluations during the design phase of the contract, the designer (Jacobs Engineering) was required to evaluate replacement of the existing SFE pump station, right sizing the facility, and evaluate benefits for treating SFE water.    

JUSTIFICATION

The scope of the phase 1 work with a tentative finish date of September 25, 2023 (148 days ahead of schedule), includes, but is not limited to the following:

                     Increase redundancy of the disinfection system by adding a sodium hypochlorite feed connection from the Hypo building to the chlorine carrier water junction chamber.

                     Increase resiliency by providing backup water for both the intermediate and high-pressure secondary water supplies.

                     Determine the risks of using SFE for chlorine carrier water vs. costs to treat.

                     Conduct field surveys of the Water Resource Recovery Facility (WRRF) to identify opportunities for water reduction and conservation.

                     Redesign new SFE pump station to include future (uninstalled) capacity and increase access to equipment. 

The above listed items were identified after the project scope was developed. The additional design features are necessary for the project to insure reliable operations of the system.

 

PROJECT MANAGEMENT STATUS

Original Contract Time                                           1,052 Days (4/5/2021 - 2/20/2024)                     

Proposed Amendment No. 1                              0 Days

New Contract Time                                                                1,052 Days (4/5/2021 - 2/20/2024)                     

 

PROJECT ESTIMATE

Original Contract Price                                           $ 3,399,730.00

Proposed Amendment No. 1                             488,611.00

New Contract Total                                                                $ 3,888,341.00

 

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.              

Funding Source: Wastewater Construction Bond

Cost Center: Sewer Water

Expense Type: Design Build (5421-892211.000-616900-216008)

Estimated Cost by Year and Related Estimating Variance:  See table below.

Original Contract Price                                                             $3,399,730.00

Proposed Amendment No. 1                                                                                                   488,611.00

New Contract Total                                                                       $3,888,341.00

Amended Financial Plan Estimate                                        $58,300,000.00

Balance reserved for construction:                                       $57,911,659.00

 

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on June 14, 2023. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.