Title
Proposed Change Order No. 2
Contract No. 2103206
Emergency Replacement of Effluent Butterfly Valves Actuators at Seven Mile and Puritan-Fenkell CSO Facilities
I&E
Body
Agenda of: September 27, 2023
Item No.: 2023-326
Amount: Original Contract $1,280,000.00
Change Order No. 1 0.00
Proposed Change Order No. 2 45,000.00
Total Revised Contract $1,325,000.00
TO: The Honorable
Board of Directors
Great Lakes Water Authority
FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority
DATE: September 1, 2023
RE: Proposed Change Order No. 2
Contract No. 2103206
Emergency Replacement of Effluent Butterfly Valves Actuators at Seven Mile and Puritan-Fenkell CSO Facilities
Vendor: Lakeshore Global Corporation
MOTION
Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2103206, Proposed Change Order No. 2, “Emergency Replacement of Effluent Butterfly Valves Actuators at Seven Mile and Puritan-Fenkell CSO Facilities” with Lakeshore Global Corporation, for an increased cost of $45,000.00 for a total cost not to exceed $1,325,000.00 and an increased duration of 93 days for a total contract duration of 483 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
During wet weather and high river level events, the effluent chamber actuators and controls are submerged, rendering the gates inoperable and causing potential floods and disrupting operations. This project includes actuator controls and gate improvements to alleviate this concern.
JUSTIFICATION
During installation of the new seals, blistering and deterioration of the gate frame was discovered. This deterioration could damage the seals in the future. This amendment is to allow time and additional cost to repair the gate frame for proper sealing of the gates.
PROJECT MANAGEMENT STATUS
Original Contract Time 330 days (07/06/2022 - 05/31/2023)
Change Order No. 1 60 days (06/01/2023 - 07/30/2023)
Proposed Change Order No. 2 93 days (07/31/2023 - 10/31/2023)
New Contract Time 483 days (07/06/2022 - 10/31/2023)
PROJECT ESTIMATE
Original Contract Price $ 1,280,000.00
Change Order No. 1 0.00
Proposed Change Order No. 2 45,000.00
New Contract Total $ 1,325,000.00
FINANCIAL PLAN IMPACT
Summary: This emergency contract, change orders, and the extensions of time were not anticipated during the development of the FY 2023 and FY 2024 budgets. Budget amendments were put forth for this project. First, offsetting other positive variances within the Combined Sewer Overflow facilities’ (CSO) budgets, then from other areas, and finally from the unallocated reserves. A portion of the O&M estimated costs is anticipated to be reimbursed as outlined in the Grant Application Status section below:
Funding Source: Operations and Maintenance (O&M) - 5960
Improvement and Extension (I&E) - 5404
Cost Center(s): Puritan Fenkell Combined Sewer Overflow (892271)
Seven Mile Combined Sewer Overflow (892272)
Expense Type(s): Repairs & Maintenance - Equipment (622300)
Repairs & Maintenance - Facilities (622400)
Capital Outlay over $5k (I&E-Capitalized) (901100)
Estimated Cost by Year and Related Forecast Variance: See table below.
Fiscal Year O&M Amount I&E Amount Total
FY 2023 Amended Budget $572,600.00 $797,090.96 $1,369,690.96
FY 2024 Budget (Prorated) 67,732.20 68,000.00 135,732.20
Total Financial Plan 640,332.20 865,090.96 1,505,423.16
Maximum Contract $492,234.71 $832,765.29 $1,325,000.00
Variance (positive/(negative)) $148,097.49 $32,325.67 $180,423.16
GRANT APPLICATION STATUS
GLWA has applied for two grants through the State of Michigan which will be funded through the Federal Emergency Management Agency (FEMA) and are related to the June 2021 flood events. The grants are associated with expenditures made to mitigate future flood damage at the Seven Mile and Puritan-Fenkell CSO facilities. These grants, and all other grants, are included in a Grants, Gifts and Other Resources Report provided to the Audit Committee monthly.
The Grants, Gifts and Other Resources Report has aligned language related to the grant lifecycle with best practices related and the Workday system being implemented. The grants lifecycle refers to the process required to secure, administer, and close out grant activity. These steps are broken down into three major phases: pre-award, award, and post-award.
The pre-award phase includes the process of applying for a grant and the period prior to the signing of the grant agreement between the awarding agency and GLWA.
The award phase reflects the period after the agreement is executed with the awarding agency. In this phase, GLWA becomes responsible for meeting the administrative, financial, and programmatic reporting requirements of the award.
The post-award phase is the final stage of grant activity and includes final reporting requirements, auditing, and closeout. There are final financial and programmatic reports that must be submitted to formally close out the grant as defined in each grant agreement.
The Seven Mile CSO grant has been awarded in the amount of $49,996.16 and this amount was received on June 30, 2023. The Puritan Fenkell CSO grant has been applied for and is in the pre-award phase. The grant amount applied for is $80,128.72 and GLWA is waiting for notice of award at this time.
COMMITTEE REVIEW
This item is being presented directly to the GLWA Board of Directors.
SHARED SERVICES IMPACT
This item does not impact the shared services agreement between GLWA and DWSD.