Skip to main content
Great Lakes Water Authority Logo
File #: 2025-146    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/28/2025 In control: Board of Directors
On agenda: 5/28/2025 Final action: 5/28/2025
Title: Proposed Change Order No. 1 Contract No. 2100239/SCN-0000417 WRRF Facilities Structural Evaluation and Repairs CIP #216011/BCE Score: 64.40
Sponsors: Navid Mehram
Indexes: Wastewater Operations

Title

Proposed Change Order No. 1

Contract No. 2100239/SCN-0000417

WRRF Facilities Structural Evaluation and Repairs

CIP #216011/BCE Score: 64.40

 

Body                     

Agenda of:                     May 28, 2025

Item No.:                     2025-146

Amount:                     Original Contract                                                               $12,639,000.00

                                          Proposed Change Order No. 1                            750,000.00

                                          Total Contract Amount                                          $13,389,000.00                     

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     April 28, 2025

 

RE:                     Contract No.  2100239/SCN-0000417

                     WRRF Facilities Structural Evaluation and Repairs

                     Vendor: Kokosing Industrial, Inc.

                     Status: Amendment/Change Order

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2100239/SCN-0000417, Proposed Change Order No. 1, “WRRF Facilities Structural Evaluation and Repairs” with Kokosing Industrial, Inc., with an increased cost of $750,000.00 for a total cost not to exceed $13,389,000.00 with no increase in duration for a total duration of 1,735 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

GLWA awarded Contract No. 2100239, “Design-Build Contract for WRRF Structural Evaluation and Repairs”, to Kokosing Industrial, Inc. The purpose of this design-build contract is to identify and implement structural repairs required in specified areas within the Water Resource Recovery Facility (WRRF). The first phase of the project required the vendor to perform a full structural assessment of these areas, identify all structural defects, and prioritize these repairs based on the available budget in the contract, utilizing the contract unit prices. The project has successfully prioritized high-importance repairs, enhancing long-term structural reliability. However, three (3) unforeseen issues have emerged: 1. actual repair quantities exceeding initial projections, 2. failing architectural stonework at the Administration Building due to water infiltration, creating safety hazards and higher-than-expected repair costs, and 3. a significant concrete wall failure at the Aeration Basin Nos. 3 and 4 Pipe Gallery, requiring further engineering investigation to determine repair solutions.

The project team currently anticipates that a $750,000.00 increase in the Provisionary Allowance will allow the Contractor to complete known repairs as described above, as well as additional repair quantities that may be uncovered as the work progresses. The contractor’s schedule indicates that all repairs will be completed within the existing contract duration.

JUSTIFICATION

The project team has determined that an increase to the existing contract amount is necessary to achieve the project's goal of extending the structural lifespan and addressing high priority structural repairs for selected facilities at the WRRF. The final cost for the above-described items will be negotiated in accordance with the contract documents.  All unused amounts remaining in the provisionary allowance will be credited back to GLWA through a final change order.

PROJECT MANAGEMENT STATUS

Original Contract Time                                            1,735 days (10/17/2022 - 7/18/2027)

Proposed Change Order No. 1                              0 days

New Contract Time                                                                 1,735 days (10/17/2022 - 7/18/2027)

 

 

 

 

PROJECT ESTIMATE

Original Contract Price                                            $12,639,000.00

Proposed Change Order No. 1                                750,000.00

New Contract Total                                                                 $13,389,000.00

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.              

Funding Source: 5421 - Wastewater Construction Fund

Cost Center: 880000 - Capital Improvement Program

Spend Category: Construction

Project Worktag: PRJ-216011

Estimated Cost by Year and Related Estimating Variance: See table below.

 

Original Contract Price                                                              $12,639,000.00

Proposed Change Order No. 1                                                                                        750,000.000

New Contract Total                                                                         $13,389,000.00

Amended Financial Plan Estimate                                            $16,000,000.00

Balance reserved for construction:                                            $11,453,018.00

 

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on May 14, 2025. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.