File #: 2019-148    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/2/2019 In control: Board of Directors
On agenda: 4/24/2019 Final action: 4/24/2019
Title: Proposed Change Order No. 1 GLWA-CON-149 Emergency Sewer Repair CIP# 260201/O&M
Sponsors: Cheryl Porter, Todd King
Attachments: 1. CIP 260200

Title

Proposed Change Order No. 1

GLWA-CON-149

Emergency Sewer Repair

CIP# 260201/O&M

                     

Body

Agenda of:                     April 24, 2019

Item No.:                     2019-148

Amount:                     Original Contract                                                               $26,800,000.00

                                          Proposed Change Order No. 1                       26,800,000.00

                                          Total Revised Contract                                          $53,600,000.00

 

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Sue F. McCormick

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     April 3, 2019

 

RE:                                          Proposed Change Order No. 1

                     Contract No. GLWA-CON-149

                     Emergency Sewer Repair

                     Vendor:  Inland Waters Pollution Control, Inc.

 

 

MOTION

Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. GLWA-CON-149 Change Order No. 1 “Emergency Sewer Repair” with Inland Waters Pollution Control, Inc., at an increased amount of $26,800,000.00 for a total cost not to exceed $53,600,000.00 for an increased duration of two (2) years for a total contract length of four (4) years; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

 

 

BACKGROUND

The GLWA sewer system (approximately 180 miles of sewers ranging in diameter from 48-inch through 168-inch) is over 80 years old for the majority of the sewers. Because of the age of the sewers, they are susceptible to deterioration at a faster rate. Some are rated at higher PACP (Pipeline Assessment Certification Program) ratings, and immediate emergency action is often required. Sewer rehabilitation services are necessary to repair plugged, damaged and collapsed sewers to avoid basement flooding, and maintain the flows within the wastewater conveyance system.

JUSTIFICATION

Contract No. GLWA-CON-149 “Emergency Sewer Repair” is for a duration of 24 months from July 17, 2017 and will expire on July 17, 2019. The contract was advertised, approved by the Board, and executed with an option to renew for an additional 24 months based on the Contractor’s satisfactory performance, the Authority’s need for additional services, and funding availability. These tasks may be considered as Operations and Maintenance (O&M) as well as Capital Improvement Projects (CIP) based on the scope of work. Examples of major tasks have included such things as the emergency stabilization and rehabilitation of the Northwest Interceptor along Warren Avenue in Detroit, repair and rehabilitation of identified structural O&M defects identified as needing immediate attention as part of the sewer inspection performed throughout the GLWA collection system, backwater gate inspections and repair to prevent Detroit and Rouge River inflow to the collection system, and a variety of manhole, hatch and structural repairs as necessary to maintain safe conditions around GLWA collection facilities.

The purpose of this contract is to provide the means of inspection, sewer lining and open cut repair of failed sewers and in-place rehabilitation of selected sewers using the procedures, methods and equipment of the cured-in-place pipe lining process.

The Contractor has performed the work meeting or exceeding GLWA’s expectations and staff wishes to exercise the renewal option for this work to extend the contract for 24 months along with the associated annual budget of $13,400,000.00 for a total amendment of $26,800,000.00 and a new contract upper limit of $53,600,000.00.

PROJECT MANAGEMENT STATUS

Original Contract Time                                            2 Years

Change Order No. 1                                             2 Years

New Contract Time                                                                 4 Years

 

PROJECT ESTIMATE

Original Contract Price                                          $26,800,000.00

Change Order No. 1                                             26,800,000.00

New Contract Total                                                               $53,600,000.00

FINANCIAL PLAN IMPACT

Summary: The proposed contract with Inland Waters Pollution Control, Inc. encompasses Capital Improvement Plan and Operations & Maintenance expenses.  The value of the contract is within the current financial plan in total.  Sufficient funds will be provided in the Operations & Maintenance (O&M) and CIP financial plan for this contract related to contractual operating services.

 

Funding Source:  Operations & Maintenance (O&M) Budget; CIP 260200  

 

Cost Center(s): Field Service Operations…....Centralized Services cost center 882431

 

Expense Type(s): Contractual Operating Services (617900); Construction (616900)

                     

Estimated Cost by Year and Related Estimating Variance:  See table below.

Fiscal Year                                                                                     CIP                                               O&M                                           Total

FY 2018 Budget                                                                      $7,400,000                      $5,960,000                           $13,360,000

FY 2019 Budget                                                                        7,400,000                        5,960,000                             13,360,000

FY 2020 Financial Plan                                                   7,400,000                        6,160,800                             13,560,800

FY 2021 Financial Plan                                                   7,400,000                        6,281,600                             13,681,600

Total O&M Final Plan Estimate     $29,600,000      $24,362,400                           $53,962,400

Proposed O&M Contract Amount  $29,760,000      $23,840,000                           $53,600,000

Variance (positive/(negative))                           $   (160,000)      $     522,400                           $     362,400

 

SAVINGS, COST OPTIMIZATION, AND REVENUE ENHANCEMENT IMPACT

 

The award of this contract provides an O&M variance of $522,400 ($24,362,400 financial plan estimate less $23,840,000 proposed contract amount) and a CIP variance of ($160,000) to be funded from the unallocated portion of CIP Program 260200.  Contractual services are dependent on several factors such as, delays in estimated start and end dates, environmental constraints, and other unforeseen circumstances that can cause the expenses to fluctuate from fiscal year to fiscal year.

 

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on April 11, 2019.  The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.