Great Lakes Water Authority Logo
File #: 2025-128    Version: 1 Name:
Type: Resolution Status: New Business
File created: 4/4/2025 In control: Board of Directors
On agenda: 4/23/2025 Final action:
Title: Proposed Change Order No. 2 Contract No. 2201744/SCN-0000118 Front Entrance Rehabilitation at the Water Resource Recovery Facility CIP #260903 / BCE Score: 52.40
Sponsors: Navid Mehram
Indexes: Wastewater Operations

Title

Proposed Change Order No. 2

Contract No. 2201744/SCN-0000118

Front Entrance Rehabilitation at the Water Resource Recovery Facility

CIP #260903 / BCE Score: 52.40

 

Body

Agenda of:                     April 23, 2025

Item No.:                     2025-128

Amount:                     Original Contract Amount                                                                                    $6,997,000.00

                                                   Change Order No. 1                                                           0.00

                      Proposed Change Order No. 2                                                               $1,370,146.00

                      Total Contract Amount                                                                                    $8,367,146.00

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     April 4, 2025

 

RE:                     Contract No. 2201744/SCN-0000118

Front Entrance Rehabilitation at the Water Resource Recovery Facility

Vendor: Commercial Contracting Corporation

Status: Amendment/Change Order

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2201744/SCN-0000118, Proposed Change Order No. 2, “Front Entrance Rehabilitation at the Water Resource Recovery Facility” with Commercial Contracting Corporation, with an increase in cost of $1,370,146.00 for a total cost not to exceed $8,367,146.00 and an increased duration of 425 days for a total duration of  1,020 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

On September 15, 2023, GLWA issued the Notice to Proceed for Contract No. 2201744, to Commercial Contracting Corporation (CCC).  The project identified by the Wastewater master plan is intended to transform the appearance of the front entrance area for GLWA’s Water Resource Recovery Facility (WRRF), which was last constructed and updated in 1980.  The WRRF is the largest single site wastewater treatment facility in the United States and the front entrance area is the main point of entry to the facility for the vast majority of the individuals that enter the facility.  The project includes upgrades to the existing guard shack, turnstiles, fencing, parking structure entrance, guest parking, and canopies. Also included is the repair of the surge basin concrete and installation of a new elevated ventilation stack structure.  The surge basin protects the WRRF in the event of pumping loss. The surge basin was installed in 1938 and is positioned under a large portion of the front entrance.  As of last month, CCC completed the surge basin repairs and modifications of the front surface parking lot.  CCC has continued work on the parking structure entrance, excavation for the foundations for the new canopies, and removed the existing turnstiles, which equates to roughly 36% of the entire project scope.

JUSTIFICATION

Based upon the current status of the project, the agreed upon final completion milestone will not be achieved.  There have been several unforeseen conditions, including permit acquisition delays, canopy supplier issues, surge basin work delays, exploratory excavation, design conflicts with found conditions, and contractor delays which have contributed to the delay of the project.  Upon execution of this proposed change order, an additional cost in the existing contract provisional allowance will enable the contractor to provide the additional requested scope items related to the guardhouse, courtyard sidewalk, and mural.  Additionally, the contractor will be able to complete the revisions to the project necessitated by the differing site conditions found during construction.  These revisions include relocation of utilities, installation of the concrete duct banks, foundation underpinning, and revisions to the design of the elevated ventilation stack structure as well as both canopies.  Therefore, Wastewater Engineering recommends the extension in time and supports the additional cost. Portions of the provisional allowance have already been utilized, and the Wastewater Engineering team intends to retain the remaining amount, as a significant portion of the project still needs to be completed. All unused funds from the provisional allowance will be credited back to GLWA via the final change order as part of the project closeout phase.                      

PROJECT MANAGEMENT STATUS

Original Contract Time                                              366 days (09/15/2023 - 09/14/2024)

Change Order No. 1                                              229 days (09/15/2024 - 05/01/2025)

Proposed Change Order No. 2                        425 days (05/02/2025 - 06/30/2026)

New Contract Time                                                                1,020 days (09/15/2023 - 06/30/2026)

PROJECT ESTIMATE

Original Contract Price                                              $6,997,000.00

Change Order No. 1                                                                  0.00

Proposed Change Order No. 2                          1,370,146.00

New Contract Total                                                                   $8,367,146.00

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.              

Funding Source: 5421 - Wastewater Construction Fund

Cost Center: 880000 - Capital Improvement Program

Spend Category: Construction

Project Worktag: PRJ-260903

Estimated Cost by Year and Related Estimating Variance:  See table below.

Original Contract Price                                                              $6,997,000.00

Change Order No. 1                                                                                  0.00

Proposed Change Order No. 2                                                                                                  1,370,146.00

New Contract Total                                                                         $8,367,146.00

Amended Financial Plan Estimate                                            $6,997,000.00

Estimating Variance:                                                                ($1,370,146.00)

The award of this proposed change order to the vendor creates a negative estimating variance of $1,370,146.00. This variance will be funded from capital reserves.

 

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on April 10, 2025. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.