File #: 2023-366    Version: 1 Name:
Type: Resolution Status: Passed
File created: 10/2/2023 In control: Board of Directors
On agenda: 10/25/2023 Final action: 10/25/2023
Title: Proposed Change Order No. 2 Contract No. 2003330 HVAC and Odor Control Improvements, Oakwood CSO CIP #260618/BCE Score: 20.0
Sponsors: Navid Mehram
Indexes: Wastewater Operations

Title

Proposed Change Order No. 2

Contract No. 2003330

HVAC and Odor Control Improvements, Oakwood CSO                     

CIP #260618/BCE Score:  20.0

 

Body

Agenda of:                      October 25, 2023

Item No.:                     2023-366

Amount:                     Original Contract                                                                                    $5,492,000.00

                                          Change Order No. 1                                                                    500,000.00

                                          Proposed Change Order No. 2                                                          0.00

                                          Total Revised Contract                                                               $5,992,000.00                                                                                                                                                                                                                  

TO:                                          The Honorable

Board of Directors

Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                                          Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     October 2, 2023

 

RE:                                          Proposed Change Order No. 2

                     Contract No. 2003330

                     HVAC and Odor Control Improvements, Oakwood CSO

                     Vendor:  Commercial Contracting Corporation

                     Designer:  Hazen and Sawyer

 

MOTION

 

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2003330, Proposed Change Order No. 2, “HVAC and Odor Control Improvements, Oakwood CSO” with Commercial Contracting Corporation, with no increase in cost for a total  cost not to exceed $5,992,000.00 and an increased duration of 183 days for a total duration of 1,015 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

The Oakwood HVAC project includes many improvements to the Oakwood HVAC system for the sanitary pump station and electrical rooms at the Oakwood CSO Facility.  The first change order was issued in September of 2022 extending the contract for the completion of additional scope of work from a failed air handling unit in the electrical room.  The extension allowed additional time to provide and startup a new air handling unit as well as time to ensure all other remaining items of the contract were completed.

As of September 30, 2023, the Contractor has not met final or substantial completion requirements.  GLWA project management has been working with the Contractor to resolve the outstanding items related to the new air handling unit and the vibration sensors for the exhaust fans on the basin. 

JUSTIFICATION

To meet GLWA Contractual requirements of being on site, the contract must be updated with a new end date of the contract which governs performance of the work, but not the completion of the work.  Currently, GLWA project management is assessing whether liquidated damages against the Contractor will become necessary.

The contract closeout change order will establish the final value of the contract which will subtract liquidated damages assessed, if any, against the final value of the contract.

PROJECT MANAGEMENT STATUS

Original Contract Time                                           481 days (06/21/2021 - 10/14/2022)

Change Order No. 1                                          351 days (10/15/2022 - 09/30/2023)

Proposed Change Order No. 2                     183 days (10/01/2023 - 03/31/2024)

New Contract Time                                                   1,015 days (06/21/2021 - 03/31/2024)

PROJECT ESTIMATE

Original Contract Price                                           $ 5,492,000.00

Change Order No. 1                                                 500,000.00

Proposed Change Order No. 2                                                0.00

New Contract Total                                                                $ 5,992,000.00

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.             

Funding Source: Sewer Construction Fund

Cost Center: Wastewater

Expense Type: Construction (5421-892211.000-616900-260618)

Estimated Cost by Year and Related Estimating Variance:  See table below.

Original Contract Price                                                            $5,492,000.00

Change Order No. 1                                                                                                                        500,000.00

Proposed Change Order No. 2                                                                               0.00

New Contract Total:                                                                                                         $5,992,000.00

This proposed Change Order No. 2 is for time extension only and has no impact on financial plan.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on October 11, 2023. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.