Skip to main content
Great Lakes Water Authority Logo
File #: 2026-004    Version: 1 Name:
Type: Resolution Status: New Business
File created: 1/5/2026 In control: Operations and Resources Committee
On agenda: 1/14/2026 Final action:
Title: Proposed Change Order No. 1 Contract No. 2004674/SCN-0000441 Engineering, Design, and Construction Assistance Services for North Service Center Pump Station Improvements CIP #132016 / BCE Score: 98.70
Sponsors: Cheryl Porter
Indexes: Water Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Proposed Change Order No. 1

Contract No. 2004674/SCN-0000441

Engineering, Design, and Construction Assistance Services for North Service Center Pump Station Improvements

CIP #132016 / BCE Score: 98.70

 

Body

Agenda of:                     January 28, 2026

Item No.:                     2026-004

Amount:                     Original Contract Amount:                                           $14,831,090.36

                                          Proposed Change Order No.1                            180,658.00

                                          Total Contract Amount                                           $15,011,748.36

 

TO:                                          The Honorable

                                          Board of Directors

                                          Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                                          Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     January 5, 2026

 

RE:                                          Proposed Change Order No. 1

                                          Contract No. 2004674/SCN-0000441

                                          Engineering, Design, and Construction Assistance Services for North Service Center Pump Station Improvements

                                          Vendor: CDM Smith Michigan, Inc.

                                          Status: Amendment/Change Order

 

 

MOTION

Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2004674/SCN-0000441, Proposed Change Order No. 1, “Engineering, Design, and Construction Assistance Services for North Service Center Pump Station Improvements” with CDM Smith Michigan, Inc., for an increased cost of $180,658.00 for a cost not to exceed $15,011,748.36 and no increase in duration for a total duration of 2,545 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

Contract No. 2004674 is a design-bid-build contract focused on the rehabilitation of the North Service Center Pumping Station. The rehabilitation will improve electrical reliability and efficiency. Electrical improvements will include replacement of two (2) switchgears, two (2) variable drives, a unit substation, four (4) excitation systems, and various panelboards. Mechanical improvements include replacement of six (6) horizontal split case pumps and their 2,500 horsepower motors, replacement of pump suction and discharge piping and valves, and addition of a discharge header. Yard piping modifications and operational flexibility by the addition of isolation valves. Control improvements will integrate new electrical and mechanical equipment for operation. Contract No. 2004674 will be substantially completed by July 31, 2031.

JUSTIFICATION

The intent of the funds requested in this Change Order is to replenish the Provisional Allowance.  Field Order No. 4 was issued to complete a redesign of vibration monitoring devices to align with GLWA's most current, and newly issued, standards.  These funds will address design changes necessary to complete the design.

PROJECT MANAGEMENT STATUS

Original Contract Time                                           2,545 days                     (10/28/2022 - 10/16/2029)

Proposed Change Order No. 1                              0 days

New Contract Time                                                                2,545 days                     (10/28/2022 - 10/16/2029)

PROJECT ESTIMATE

Original Contract Price                                           $14,831,090.36

Proposed Change Order No. 1                              180,658.00

New Contract Total                                                                $15,011,748.36

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.

Funding Source: 5519 - Water Construction Fund

Cost Center: 880000 - Capital Improvement Program

Spend Category: Construction

Project Worktag: PRJ-132016

Estimated Cost by Year and Related Estimating Variance:  See table below.

Original Contract Price                                                                                                         $14,831,090.36

Proposed Change Order No. 1                                                                                           180,658.00

New Contract Total                                                                                                                              $15,011,748.36

Amended Financial Plan Estimate                                                                 14,831,000.00

Estimating Variance                                                                                                                                  ($180,748.36)

The award of this Proposed Change Order to the vendor creates a negative estimating variance of $180,748.36, This variance will be funded from capital reserves.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on January 14, 2026.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.